17130 W COVELLO ST 91406

Certificate Information: 17130 W COVELLO ST 91406

Application / Permit
25010-20000-05735
Plan Check / Job No.
B25VN34923
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached 689 SF 2 Bedrooms + 2 Bathrooms ADU per GC 66323(a)(2). All work per WFPP.
Permit Issued
Issued on 2/26/2026
Issuing Office
Current Status
CofO in Progress on 7/15/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/1/2025 APPLICANT
Assigned to Plan Check Engineer 12/4/2025 NGHI SU
Corrections Issued 12/5/2025 NGHI SU
Plan Check Approved 2/3/2026 NGHI SU
Issued 2/26/2026 APPLICANT
CofO in Progress 7/15/2026 MICHAEL CORTEZ

Permit Application Clearance Information

Address approval Cleared 1/14/2026 DAVID LOPEZ
Roof/Waste drainage to street Cleared 1/14/2026 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 1/15/2026 DAVID LOPEZ
Sewer availability Cleared 1/15/2026 DAVID LOPEZ
Construction near power lines Cleared 1/31/2026 GEVORK KARAPETYAN
Construction within easement Cleared 1/31/2026 GEVORK KARAPETYAN

Contact Information

Contractor First Stop Construction Inc; Lic. No.: 1014721-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/11/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Sewer 3/11/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/18/2026 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 3/18/2026 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/2/2026 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 4/22/2026 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/22/2026 Approved KIRK SANDERS
HVAC-Rough 4/22/2026 Corrections Issued KIRK SANDERS
PLUMBING-Rough 4/22/2026 Approved KIRK SANDERS
ELECTRICAL-Rough 4/24/2026 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 4/24/2026 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 4/24/2026 Not Ready for Inspection MATTHEW NELSON
Wood Frame 4/24/2026 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 4/27/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 4/27/2026 Approved KIRK SANDERS
HVAC-Rough 4/27/2026 Approved KIRK SANDERS
Insulation 4/29/2026 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 4/29/2026 Partial Approval MICHAEL CORTEZ
BUILDING-Rough-Frame 5/1/2026 Partial Approval KIRK SANDERS
Insulation 5/1/2026 Approved KIRK SANDERS
Drywall Nailing 5/4/2026 Approved MICHAEL CORTEZ
Shower Pan 5/12/2026 Approved MICHAEL CORTEZ
Underground Mechanical 5/22/2026 Approved MICHAEL CORTEZ
Final 7/1/2026 Corrections Issued MICHAEL CORTEZ
Green Building Final 7/1/2026 Corrections Issued MICHAEL CORTEZ
Green Building Rough 7/1/2026 Approved MICHAEL CORTEZ
Smoke Detectors 7/1/2026 Corrections Issued MICHAEL CORTEZ
Verify Sprinkler Sign Off 7/1/2026 Approved MICHAEL CORTEZ
Final 7/8/2026 Not Ready for Inspection MICHAEL CORTEZ
BUILDING-Rough-Frame 7/14/2026 Approved MICHAEL CORTEZ
ELECTRICAL-Final 7/14/2026 Approved MICHAEL CORTEZ
Final 7/14/2026 OK to Issue CofO MICHAEL CORTEZ
Footing/Foundation/Slab 7/14/2026 Approved MICHAEL CORTEZ
Green Building Final 7/14/2026 Approved MICHAEL CORTEZ
HVAC-Final 7/14/2026 Approved MICHAEL CORTEZ
PLUMBING-Final 7/14/2026 Approved MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 7/14/2026 SGSOV Not Required MICHAEL CORTEZ
Service/Power Release 7/14/2026 Approved MICHAEL CORTEZ
Smoke Detectors 7/14/2026 Approved MICHAEL CORTEZ