20621 W SCHOENBORN ST 91306
Certificate Information: 20621 W SCHOENBORN ST 91306
- Application / Permit
- 25010-20000-05727
- Plan Check / Job No.
- B25VN34866
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 20' X 21' 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC12.22A.33(b)(1). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/11/2026
- Issuing Office
- Current Status
- Issued on 5/11/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/7/2025 | APPLICANT |
| Assigned to Zoning Architect | 12/19/2025 | ELAHE MERRIKHI |
| Assigned to Plan Check Engineer | 12/24/2025 | RAPHAEL ROSAS |
| Corrections Issued | 12/30/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 12/30/2025 | STEVEN KIM |
| Applicant returned to address corrections | 1/29/2026 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/17/2026 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/7/2026 | RAPHAEL ROSAS |
| Plan Check Approved | 5/1/2026 | RAPHAEL ROSAS |
| Issued | 5/11/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2026 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 1/22/2026 | WALLIE JONG |
| Zoning Plan Check | Cleared | 3/20/2026 | ELAHE MERRIKHI |
| Construction near power lines | Cleared | 4/4/2026 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2026 | WALLIE JONG |
| Sewer availability | Cleared | 4/27/2026 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/9/2026 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 6/12/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/17/2026 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2026 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/10/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 7/10/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |