5618 N BUFFALO AVE 91401

Certificate Information: 5618 N BUFFALO AVE 91401

Application / Permit
25010-20000-05723
Plan Check / Job No.
B25VN34818
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SB9 WITH ATTACHED TWO CAR GARAGE
Permit Issued
Issued on 1/20/2026
Issuing Office
Current Status
Issued on 1/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/1/2025 APPLICANT
Assigned to Plan Check Engineer 12/4/2025 VARAND SARKISIAN
Assigned to Zoning Architect 12/4/2025 CAMERON JONES
Corrections Issued 12/8/2025 VARAND SARKISIAN
Quality Review Completed 12/12/2025 GARO TELMI
Plan Check Approved 1/20/2026 VARAND SARKISIAN
Issued 1/20/2026 APPLICANT

Permit Application Clearance Information

Senate Bill 9 Cleared 12/30/2025 BRENNEN OBETO
Address approval Cleared 1/2/2026 JEREMY CHOK
Permit Cleared 1/2/2026 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 1/6/2026 JEANIE LAM
Roof/Waste drainage to street Cleared 1/6/2026 JEANIE LAM
Sewer availability Cleared 1/6/2026 JEANIE LAM
Hydrant and Access approval Cleared 1/7/2026 GILBERT URREA
Zoning Plan Check Cleared 1/9/2026 CAMERON JONES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/2/2026 Approved VINCENT HANLEY
PLUMBING-Rough 2/9/2026 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 2/25/2026 Conditional Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 2/25/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/17/2026 Partial Approval VINCENT HANLEY
Green Building Rough 3/17/2026 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 3/17/2026 Not Ready for Inspection VINCENT HANLEY
Wood Frame 3/17/2026 Partial Approval VINCENT HANLEY
Deputy Wood Construction 3/26/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/1/2026 Approved VINCENT HANLEY
HVAC-Rough 4/9/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/9/2026 Partial Approval VINCENT HANLEY
PLUMBING-Rough 4/9/2026 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/14/2026 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/21/2026 Approved VINCENT HANLEY
Green Building Rough 4/21/2026 Approved VINCENT HANLEY
Shower Pan 4/21/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/21/2026 Approved VINCENT HANLEY
Insulation 4/27/2026 Approved VINCENT HANLEY
Drywall Nailing 5/4/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/4/2026 Approved VINCENT HANLEY