5618 N BUFFALO AVE 91401
Certificate Information: 5618 N BUFFALO AVE 91401
- Application / Permit
- 25010-20000-05723
- Plan Check / Job No.
- B25VN34818
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SB9 WITH ATTACHED TWO CAR GARAGE
- Permit Issued
- Issued on 1/20/2026
- Issuing Office
- Current Status
- Issued on 1/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2025 | VARAND SARKISIAN |
| Assigned to Zoning Architect | 12/4/2025 | CAMERON JONES |
| Corrections Issued | 12/8/2025 | VARAND SARKISIAN |
| Quality Review Completed | 12/12/2025 | GARO TELMI |
| Plan Check Approved | 1/20/2026 | VARAND SARKISIAN |
| Issued | 1/20/2026 | APPLICANT |
Permit Application Clearance Information
| Senate Bill 9 | Cleared | 12/30/2025 | BRENNEN OBETO |
| Address approval | Cleared | 1/2/2026 | JEREMY CHOK |
| Permit | Cleared | 1/2/2026 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2026 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 1/6/2026 | JEANIE LAM |
| Sewer availability | Cleared | 1/6/2026 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/7/2026 | GILBERT URREA |
| Zoning Plan Check | Cleared | 1/9/2026 | CAMERON JONES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/2/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/9/2026 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 2/25/2026 | Conditional Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 2/25/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2026 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/17/2026 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 3/17/2026 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 3/17/2026 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 3/17/2026 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 3/26/2026 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/9/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/9/2026 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/9/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/14/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/21/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/21/2026 | Approved | VINCENT HANLEY |
| Shower Pan | 4/21/2026 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 4/21/2026 | Approved | VINCENT HANLEY |
| Insulation | 4/27/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/4/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/4/2026 | Approved | VINCENT HANLEY |