136-136 1/2 E 82ND PL 90003
Certificate Information: 136-136 1/2 E 82ND PL 90003
- Application / Permit
- 25010-20000-05720
- Plan Check / Job No.
- B25VN34816
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* (2) NEW DETACHED TWO-STORY ACCESSORY DWELLING UNITS PER GCS 66323(a)(4).
- Permit Issued
- Issued on 5/29/2026
- Issuing Office
- Current Status
- Issued on 5/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2025 | ZENA HADDIS |
| Assigned to Zoning Architect | 12/4/2025 | LINGHUI YU |
| Corrections Issued | 12/9/2025 | SELLA BENYAMIN |
| Quality Review Completed | 12/11/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 4/2/2026 | MADISON ODELL |
| Applicant returned to address corrections | 5/28/2026 | ZENA HADDIS |
| Plan Check Approved | 5/29/2026 | ZENA HADDIS |
| Issued | 5/29/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 12/15/2025 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2026 | JEANIE LAM |
| Sewer availability | Cleared | 1/13/2026 | JEANIE LAM |
| Zoning Plan Check | Cleared | 1/21/2026 | LINGHUI YU |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | , |
| Engineer | Basma,, Jad; Lic. No.: C96371 | 1149 S BROADWAY 6TH FLOOR LOS ANGELES, CA 90015 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/3/2026 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 6/3/2026 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 6/4/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 6/5/2026 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 6/5/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2026 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2026 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/1/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 7/1/2026 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 7/2/2026 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/7/2026 | Approved | BARRY HACHE |
| Green Building Rough | 7/7/2026 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 7/7/2026 | Approved | BARRY HACHE |
| Insulation | 7/9/2026 | Corrections Issued | WILLIAM SIERRA |
| Interior/Exterior Lathing | 7/9/2026 | Partial Approval | WILLIAM SIERRA |
| Insulation | 7/13/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 7/13/2026 | Approved | ALEX COLIN |
| Drywall Nailing | 7/15/2026 | No Access for Inspection | JOHN QUINTANILLA |
| Drywall Nailing | 7/17/2026 | Approved | SALVADOR MARTINEZ |