22120 W SATICOY ST 91303
Certificate Information: 22120 W SATICOY ST 91303
- Application / Permit
- 25010-20000-05638
- Plan Check / Job No.
- B25VN34531
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (b)(1),(c),(d),(h) and (k).
- Permit Issued
- Issued on 1/28/2026
- Issuing Office
- Current Status
- Issued on 1/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2025 | ROSENDO MEDINA |
| Corrections Issued | 12/2/2025 | ROSENDO MEDINA |
| Plan Check Approved | 12/11/2025 | ROSENDO MEDINA |
| Issued | 1/28/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/3/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2025 | WALLIE JONG |
| Sewer availability | Cleared | 12/11/2025 | WALLIE JONG |
Contact Information
| Contractor | Sharp Builders & Son; Lic. No.: 1144723-B | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/6/2026 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/10/2026 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2026 | Approved | JEFFREY HARTLINE |
| Sewer | 2/27/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 3/26/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/27/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 3/27/2026 | Approved | JEFFREY HARTLINE |
| Rough-Elec/Plmb/HVAC | 3/27/2026 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 3/27/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/31/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 3/31/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/31/2026 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 4/7/2026 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 4/13/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 4/13/2026 | Partial Approval | JEFFREY HARTLINE |