14378 W GERMAIN ST 91345
Certificate Information: 14378 W GERMAIN ST 91345
- Application / Permit
- 25010-20000-05580
- Plan Check / Job No.
- B25VN34314
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. (N) Detached Accessory Dwelling Unit per GC 66323(a)(2)
- Permit Issued
- Issued on 1/21/2026
- Issuing Office
- Current Status
- Issued on 1/21/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2025 | AMY GUEVARRA |
| Corrections Issued | 12/1/2025 | AMY GUEVARRA |
| Assigned to Zoning Architect | 12/2/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 1/8/2026 | AMY GUEVARRA |
| Plan Check Approved | 1/15/2026 | AMY GUEVARRA |
| Issued | 1/21/2026 | APPLICANT |
Permit Application Clearance Information
| Construction within easement | Cleared | 12/4/2025 | WALTER RAMIREZ |
| Address approval | Cleared | 12/15/2025 | TONY CHIANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2025 | TONY CHIANG |
| Roof/Waste drainage to street | Cleared | 12/15/2025 | TONY CHIANG |
| Sewer availability | Cleared | 12/15/2025 | TONY CHIANG |
| Zoning Plan Check | Cleared | 1/15/2026 | Sunmin Lee |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Sewer | 6/9/2026 |
Inspection Request History
| Pre-Inspection | 2/2/2026 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/6/2026 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/13/2026 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Barrier | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/26/2026 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/26/2026 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 3/2/2026 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 3/3/2026 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2026 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/19/2026 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 3/19/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 3/19/2026 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 3/19/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/26/2026 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/26/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/26/2026 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 3/26/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/26/2026 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/2/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/2/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/2/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/2/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/2/2026 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/2/2026 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/9/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/14/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 4/23/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/30/2026 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 4/30/2026 | Approved | JENNIFER RABUCHIN |