12003 N RED HAWK LANE 91326
Certificate Information: 12003 N RED HAWK LANE 91326
- Application / Permit
- 25010-20000-05440
- Plan Check / Job No.
- B25VN33565
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW DETACHED LATTICE PATIO COVER (TRELLIS) PER ENGINEER DESIGN.
- Permit Issued
- Issued on 2/9/2026
- Issuing Office
- Current Status
- Issued on 2/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 11/22/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 11/24/2025 | APPLICANT |
| Plan Check Approved | 2/9/2026 | OMAR GARNICA |
| Issued | 2/9/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 12/5/2025 | MICHAEL BROWN |
| Grading Pre-Inspection | Cleared | 12/5/2025 | CHARLES POWELL |
| "T" removal | Cleared | 2/5/2026 | DORIAN AGUILAR |
| CPC | Cleared | 2/5/2026 | DORIAN AGUILAR |
| Miscellaneous | Cleared | 2/5/2026 | DORIAN AGUILAR |
| Miscellaneous | Cleared | 2/5/2026 | DORIAN AGUILAR |
| ZA Case | Cleared | 2/5/2026 | DORIAN AGUILAR |
| ZI | Cleared | 2/5/2026 | DORIAN AGUILAR |
| ZI | Cleared | 2/5/2026 | DORIAN AGUILAR |
Contact Information
| Contractor | Alum Works; Lic. No.: 1110438-B | 129 LOMA LN UNIT B SAN CLEMENTE, CA 92672 |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/12/2026 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/16/2026 | Approved | JEFFREY PARD |
| Final | 3/16/2026 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 3/16/2026 | Approved | JEFFREY PARD |
| Smoke Detectors | 3/16/2026 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 3/16/2026 | Approved | JEFFREY PARD |
| Final | 5/22/2026 | Partial Approval | JEFFREY PARD |