6352-6354 N LEDERER AVE 91367
Certificate Information: 6352-6354 N LEDERER AVE 91367
- Application / Permit
- 25010-20000-05294
- Plan Check / Job No.
- B25VN30316
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: NEW 1-STORY (54'-6" X 16'-6") ACCESSORY BUILDING WITH 2 ACCESSORY DWELLING UNITS PER GC 66323(a)(4)
- Permit Issued
- Issued on 1/27/2026
- Issuing Office
- Current Status
- Issued on 1/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2025 | VAHAN JIVALAGIAN |
| Assigned to Zoning Architect | 10/23/2025 | RONALD GREENE |
| Corrections Issued | 11/6/2025 | VAHAN JIVALAGIAN |
| Quality Review Completed | 11/14/2025 | OMID HEDAYAT |
| Applicant returned to address corrections | 1/16/2026 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 1/26/2026 | VAHAN JIVALAGIAN |
| Plan Check Approved | 1/27/2026 | VAHAN JIVALAGIAN |
| Issued | 1/27/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/3/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/3/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/4/2025 | LEE GUILBEAUX |
| Zoning Plan Check | Cleared | 1/12/2026 | Ronald Greene |
Contact Information
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/6/2026 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 2/13/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Underground Mechanical | 2/13/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Underground Mechanical | 2/27/2026 | Approved | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 3/11/2026 | Corrections Issued | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 3/17/2026 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2026 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 4/9/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/9/2026 | Approved | TROY SANDERS |
| Green Building Rough | 4/9/2026 | Approved | TROY SANDERS |
| HVAC-Rough | 4/9/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 4/9/2026 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 4/9/2026 | Approved | TROY SANDERS |
| Shower Pan | 4/9/2026 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 4/9/2026 | Approved | TROY SANDERS |
| Insulation | 4/15/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 4/15/2026 | Partial Approval | TROY SANDERS |
| Sewer | 4/20/2026 | Approved | TROY SANDERS |
| Insulation | 5/7/2026 | Approved | TROY SANDERS |
| Drywall Nailing | 5/13/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 6/26/2026 | Partial Approval | TROY SANDERS |