755 E 48TH ST 90011
Certificate Information: 755 E 48TH ST 90011
- Application / Permit
- 25010-20000-05271
- Plan Check / Job No.
- B25VN32716
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2) WITH ATTACHED PATIO COVER AND COVERED PORCH. WORK PER WFPP.
- Permit Issued
- Issued on 3/18/2026
- Issuing Office
- Current Status
- Issued on 3/18/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 11/10/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 2/14/2026 | GIOVANNY CHAVEZ |
| Plan Check Approved | 3/3/2026 | OMAR GARNICA |
| Issued | 3/18/2026 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/9/2026 | RIDWAN HARDY |
| Address approval | Cleared | 1/23/2026 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2026 | JESUS CISNEROS |
| Sewer availability | Cleared | 2/4/2026 | JESUS CISNEROS |
| Roof/Waste drainage to street | Cleared | 2/12/2026 | JESUS CISNEROS |
Contact Information
| Contractor | Next Level Home Improvements; Lic. No.: 1120800-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/9/2026 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 4/9/2026 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 4/16/2026 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2026 | Partial Approval | LUIS CASTRO |
| Underground Mechanical | 5/1/2026 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/4/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/10/2026 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2026 | Approved | BRENDAN MORELLI |
| Green Building Rough | 6/10/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Rough-Elec/Plmb/HVAC | 6/10/2026 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 6/10/2026 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/22/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 6/22/2026 | Approved | SABAS ALONSO |
| Insulation | 6/22/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/22/2026 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 7/7/2026 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/8/2026 | Approved | ALEX COLIN |