Work Description
ePlan. New footings for 13 sculptures on ground floor at South Park area of the museum campus.
Permit Issued
Issued on 2/25/2026
Issuing Office
Current Status
Issued on 2/25/2026

Permit Application Status History

Submitted 11/5/2025 APPLICANT
Assigned to Plan Check Engineer 11/13/2025 TU HUA
Corrections Issued 11/15/2025 TU HUA
Quality Review Completed 11/21/2025 ARMEN JIVALAGIAN
Applicant returned to address corrections 12/30/2025 TU HUA
Applicant returned to address corrections 12/31/2025 TU HUA
Applicant returned to address corrections 2/20/2026 QUAN NGHIEM
Applicant returned to address corrections 2/23/2026 QUAN NGHIEM
Plan Check Approved 2/23/2026 QUAN NGHIEM
Issued 2/25/2026 APPLICANT

Permit Application Clearance Information

Green Code Cleared 11/5/2025 MICHAEL AYERS
DAS Clearance Cleared 2/19/2026 Minye Pak

Contact Information

Architect , ; Lic. No.: C33907       LOS ANGELES, CA 90017
Contractor Build Group Construction Company Inc; Lic. No.: 1015855-B 1324 ABBOT KINNEY BLVD      VENICE, CA 90291
Engineer Doenitz,, Halle; Lic. No.: C91458 1010 OWOSSO AVE      HERMOSA BEACH, CA 90254

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/3/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/3/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/12/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/20/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/24/2026 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/24/2026 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/1/2026 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/6/2026 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/8/2026 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 4/9/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/22/2026 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/12/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/12/2026 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/12/2026 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/13/2026 Partial Approval ALFREDO LOPEZ
Deputy Reinf. Concrete 5/13/2026 Partial Approval ALFREDO LOPEZ
Deputy Drilled-In Anchors 5/14/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/14/2026 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/14/2026 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/15/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/15/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/19/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/19/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/20/2026 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/20/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/21/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/22/2026 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/26/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/26/2026 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/27/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/27/2026 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/28/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/28/2026 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/29/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/29/2026 Partial Approval JAMES POWERS
Deputy Other (see comments) 6/5/2026 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/24/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/24/2026 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/1/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/1/2026 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/14/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/14/2026 Partial Approval JAMES POWERS