9178 N ONEIDA AVE 91352
Certificate Information: 9178 N ONEIDA AVE 91352
- Application / Permit
- 25010-20000-05231
- Plan Check / Job No.
- B25VN32469
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW DETACHED ACCESSORY DWELLING UNIT (ADU) PER GCS 66323(a)(2), ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/2/2025
- Issuing Office
- Current Status
- Issued on 12/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/8/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/2/2025 | LUISANGEL VALENZUELA |
| Issued | 12/2/2025 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 11/18/2025 | YINGSHI HUANG |
| Address approval | Cleared | 11/24/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 11/24/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 11/25/2025 | DERRICK MAGEE |
Contact Information
| Contractor | H A General Construction; Lic. No.: 1125887-B | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Final | 6/9/2026 |
| Service/Power Release | 6/9/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/11/2026 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 2/11/2026 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/13/2026 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/3/2026 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/3/2026 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/3/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/3/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/3/2026 | Approved | MATTHEW NELSON |
| Insulation | 3/6/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/6/2026 | Partial Approval | MATTHEW NELSON |
| Shower Pan | 3/6/2026 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/11/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/11/2026 | Approved | MATTHEW NELSON |
| Sewer | 4/9/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 4/10/2026 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 4/28/2026 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 4/28/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 4/28/2026 | Approved | MATTHEW NELSON |