7646 N WISH AVE 91406

Certificate Information: 7646 N WISH AVE 91406

Application / Permit
25010-20000-05222
Plan Check / Job No.
B25VN32404
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE 20'-3"X23' TWO STORY SFD SB 9 ( per SB9 Two-Unit Development Ca Govt Code 65852.21) _BUILDING SHALL BE FULLY SPRINKLER WITH NFPA 13D.
Permit Issued
Issued on 12/22/2025
Issuing Office
Current Status
Issued on 12/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/4/2025 APPLICANT
Assigned to Plan Check Engineer 11/13/2025 DAWN MC NULTY
Assigned to Zoning Architect 11/13/2025 KAITA SAITO
Corrections Issued 11/24/2025 DAWN MC NULTY
Quality Review Completed 12/1/2025 OMID HEDAYAT
Building Plans Picked Up 12/2/2025 APPLICANT
Plan Check Approved 12/22/2025 DAWN MC NULTY
Issued 12/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/24/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 11/24/2025 SAFA JAVANMARDI
Permit Cleared 11/24/2025 JESUS CISNEROS
Roof/Waste drainage to street Cleared 11/24/2025 JESUS CISNEROS
Sewer availability Cleared 11/24/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 11/26/2025 GILBERT URREA
Miscellaneous Cleared 12/10/2025 MIGUEL CRISOSTOMO
Senate Bill 9 Cleared 12/10/2025 ALEX VELA
Zoning Plan Check Cleared 12/11/2025 KAITA SAITO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/22/2026 Partial Approval GAREN HAYRAPETYAN
Underground Mechanical 1/22/2026 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 1/23/2026 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 3/13/2026 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 4/20/2026 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/20/2026 Approved KIRK SANDERS
Green Building Rough 4/20/2026 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 4/20/2026 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 4/24/2026 Approved VINCENT HANLEY
PLUMBING-Rough 4/24/2026 Approved VINCENT HANLEY
Sewer 4/24/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/28/2026 Partial Approval MICHAEL CORTEZ
BUILDING-Rough-Frame 4/30/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 4/30/2026 Corrections Issued KIRK SANDERS
Green Building Rough 4/30/2026 Approved KIRK SANDERS
HVAC-Rough 4/30/2026 Approved KIRK SANDERS
Verify Sprinkler Sign Off 4/30/2026 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 5/6/2026 Approved KIRK SANDERS
Verify Sprinkler Sign Off 5/6/2026 Approved KIRK SANDERS
Shower Pan 5/20/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 6/2/2026 Approved JOSE AVILA