7724 N VAN NUYS BLVD 91405
Certificate Information: 7724 N VAN NUYS BLVD 91405
- Application / Permit
- 25010-20000-05210
- Plan Check / Job No.
- B25VN32288
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (11) Homeless Shelter
- Work Description
- State Approved Modular Laundry Building (8'x20'). Emergency Homeless Shelter per Government Code Section 8698.4 and LAMC Section 91.8605. Tiny Home Village.
- Permit Issued
- Issued on 12/18/2025
- Issuing Office
- Current Status
- CofO Issued on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2025 | KEVIN MORALES |
| Corrections Issued | 11/12/2025 | KEVIN MORALES |
| Quality Review Completed | 11/12/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 12/2/2025 | KEVIN MORALES |
| Plan Check Approved | 12/10/2025 | KEVIN MORALES |
| Issued | 12/18/2025 | APPLICANT |
| CofO in Progress | 5/21/2026 | JOHN KITCKO |
| Permit Finaled | 5/21/2026 | RICKEY JACKSON |
| CofO Issued | 5/21/2026 | RICKEY JACKSON |
| Permit Finaled | 5/21/2026 | RICKEY JACKSON |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 11/25/2025 | KEVIN MORALES |
| Hydrant and Access approval | Cleared | 11/27/2025 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 12/3/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/3/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Ford E C Inc; Lic. No.: 396212-B | , |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/17/2026 | Partial Approval | DEANDRE HOFFMAN |
| Verify Sprinkler Sign Off | 2/17/2026 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 2/17/2026 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Not Ready | JOHN KITCKO |
| Final | 4/27/2026 | OK to Issue CofO | JOHN KITCKO |
| Footing/Foundation/Slab | 5/21/2026 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 5/21/2026 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 5/21/2026 | Approved | JOHN KITCKO |