6957 N JUMILLA AVE 91306
Certificate Information: 6957 N JUMILLA AVE 91306
- Application / Permit
- 25010-20000-05207
- Plan Check / Job No.
- B25VN32276
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION WITH SECOND STORY AND CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER ___________
- Permit Issued
- Issued on 2/26/2026
- Issuing Office
- Current Status
- Issued on 2/26/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2025 | DANIEL ABRAMYAN |
| Assigned to Zoning Architect | 11/13/2025 | SHARAREH KAHENASSA |
| Corrections Issued | 11/20/2025 | DANIEL ABRAMYAN |
| Quality Review Completed | 11/21/2025 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/26/2025 | DANIEL ABRAMYAN |
| Plan Check Approved | 2/25/2026 | DANIEL ABRAMYAN |
| Issued | 2/26/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/8/2025 | DERRICK MAGEE |
| ZI | Cleared | 12/17/2025 | ANGELA WILLIAMS |
| Zoning Plan Check | Cleared | 2/2/2026 | SHARAREH KAHENASSA |
| Address approval | Cleared | 2/12/2026 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 2/12/2026 | GEVORK KARAPETYAN |
| Public Works-Highway Ded. | Cleared | 2/12/2026 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2026 | DERRICK MAGEE |
| Sewer availability | Cleared | 2/13/2026 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/21/2026 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 4/27/2026 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 4/30/2026 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Conditional Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2026 | Conditional Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 6/10/2026 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 6/10/2026 | Conditional Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 6/10/2026 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 6/15/2026 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 6/16/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 6/16/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 6/29/2026 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 6/29/2026 | Partial Approval | ALEXANDER HANDY |
| Insulation | 7/1/2026 | Approved | TROY SANDERS |
| Shower Pan | 7/1/2026 | Approved | TROY SANDERS |
| Drywall Nailing | 7/8/2026 | Approved | TROY SANDERS |
| Green Building Rough | 7/8/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 7/8/2026 | Partial Approval | TROY SANDERS |