7314 N MCLAREN AVE 91307

Certificate Information: 7314 N MCLAREN AVE 91307

Application / Permit
25010-20000-05169
Plan Check / Job No.
B25VN32135
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW DETACHED ADU. CONSTRUCTION PER WFPP
Permit Issued
Issued on 12/10/2025
Issuing Office
Current Status
Issued on 12/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/5/2025 APPLICANT
Assigned to Plan Check Engineer 11/7/2025 KAVIAN REFAHI
Corrections Issued 11/9/2025 KAVIAN REFAHI
Applicant returned to address corrections 12/4/2025 KAVIAN REFAHI
Plan Check Approved 12/5/2025 KAVIAN REFAHI
Issued 12/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/26/2025 TONY CHIANG
Roof/Waste drainage to street Cleared 11/26/2025 TONY CHIANG
Eng Process Fee Ord 176,300 Cleared 12/2/2025 XOCHITL ARQUIETA
Sewer availability Cleared 12/2/2025 XOCHITL ARQUIETA
Construction within easement Cleared 12/3/2025 RIDWAN HARDY

Contact Information

Contractor Yor Construction And Investments Inc; Lic. No.: 978430-B       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/15/2026 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 1/20/2026 Not Ready for Inspection JEFFREY HARTLINE
Underground Mechanical 1/20/2026 Not Ready for Inspection JEFFREY HARTLINE
Footing/Foundation/Slab 1/23/2026 Approved JEFFREY HARTLINE
Underground Mechanical 1/23/2026 Partial Approval JEFFREY HARTLINE
Underground Mechanical 1/30/2026 Partial Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 2/12/2026 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 2/25/2026 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 3/5/2026 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 3/5/2026 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 3/5/2026 Not Ready for Inspection JEFFREY HARTLINE
Wood Frame 3/5/2026 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 3/9/2026 No Access for Inspection JEFFREY HARTLINE
HVAC-Rough 3/9/2026 No Access for Inspection JEFFREY HARTLINE
PLUMBING-Rough 3/9/2026 No Access for Inspection JEFFREY HARTLINE
Wood Frame 3/9/2026 No Access for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 3/10/2026 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 3/10/2026 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 3/10/2026 Approved JEFFREY HARTLINE
Wood Frame 3/10/2026 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 3/12/2026 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 3/12/2026 Approved JEFFREY HARTLINE
Green Building Rough 3/12/2026 Approved JEFFREY HARTLINE
HVAC-Rough 3/12/2026 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 3/12/2026 Approved JEFFREY HARTLINE
Insulation 3/17/2026 Approved JEFFREY HARTLINE
Drywall Nailing 3/20/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 3/27/2026 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 4/6/2026 Partial Approval JEFFREY HARTLINE
Shower Pan 4/6/2026 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 6/3/2026 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 6/3/2026 Approved JEFFREY HARTLINE
Green Building Final 6/3/2026 Not Ready for Inspection JEFFREY HARTLINE
Pre-Inspection 6/3/2026 Partial Approval JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV Not Ready JEFFREY HARTLINE
Service/Power Release 6/3/2026 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 6/3/2026 Not Ready for Inspection JEFFREY HARTLINE