9909 N TAMARACK AVE 91331

Certificate Information: 9909 N TAMARACK AVE 91331

Application / Permit
25010-20000-05160
Plan Check / Job No.
B25VN32067
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 42'-0" X 29'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 11/21/2025
Issuing Office
Current Status
Issued on 11/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/31/2025 APPLICANT
Assigned to Plan Check Engineer 11/5/2025 ARTIN ZARUKIAN
Corrections Issued 11/8/2025 ARTIN ZARUKIAN
Building Plans Picked Up 11/10/2025 APPLICANT
Plan Check Approved 11/21/2025 SAMUEL GONZALEZ
Issued 11/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/17/2025 CINDY QI
Roof/Waste drainage to street Cleared 11/17/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 11/18/2025 CINDY QI
Sewer availability Cleared 11/18/2025 CINDY QI

Contact Information

Contractor Quality Retro Construction; Lic. No.: 1033863-B 9557 NOBLE AVE      NORTH HILLS, CA 91343

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/17/2025 Corrections Issued MATTHEW NELSON
METHANE-Barrier 12/17/2025 Approved MATTHEW NELSON
METHANE-Subgrade 12/17/2025 Approved MATTHEW NELSON
Footing/Foundation/Slab 12/30/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 1/7/2026 Approved MICHEL ABAJAN
PLUMBING-Rough 1/16/2026 Partial Approval MICHEL ABAJAN
Wood Frame 1/16/2026 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 3/23/2026 Not Ready for Inspection MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 3/23/2026 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/25/2026 Approved MICHEL ABAJAN
Green Building Rough 3/25/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/25/2026 Approved MICHEL ABAJAN
METHANE-Rough 3/25/2026 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 3/25/2026 Approved MICHEL ABAJAN
Insulation 4/1/2026 Approved MICHEL ABAJAN
Drywall Nailing 4/13/2026 Approved MICHEL ABAJAN