1015-1017 N KAGAWA ST 90272

Certificate Information: 1015-1017 N KAGAWA ST 90272

Application / Permit
25010-20000-04952
Plan Check / Job No.
B25VN30987
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2025 WILDFIRE REBUILD, NEW TYPE V-A CONSTRUCTION SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e), 2-STORY AND BASEMENT, 80'-0" x 40'-0". NFPA 13D SPRINKLERS THROUGHOUT. EO1
Permit Issued
Issued on 11/25/2025
Issuing Office
Valley
Current Status
Issued on 11/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/21/2025 APPLICANT
Assigned to Plan Check Engineer 10/21/2025 RARES BODEA
Corrections Issued 10/27/2025 RARES BODEA
Quality Review Completed 10/29/2025 STEVEN KIM
Building Plans Picked Up 10/29/2025 APPLICANT
Applicant returned to address corrections 11/24/2025 RARES BODEA
Plan Check Approved 11/25/2025 RARES BODEA
Issued 11/25/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/28/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 10/28/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 10/28/2025 DAVID LOPEZ
Sewer availability Cleared 10/28/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 10/31/2025 MARTIN FRAGOSO
Hydrant and Access approval Cleared 11/17/2025 KURT CORRAL
SB8 RUD Cleared 11/18/2025 BLAKE BOULIGNY
Excavation more than 5-ft deep Cleared 11/25/2025 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/22/2026 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 1/30/2026 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 2/25/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/27/2026 Partial Approval TEMISTOCLES CAAL
Pre-Inspection 2/27/2026 Partial Inspection TEMISTOCLES CAAL
Deputy Reinf. Concrete 3/2/2026 Conditional Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 3/5/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/6/2026 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 3/12/2026 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/6/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/8/2026 Corrections Issued HERBERT GIRON
Deputy Reinf. Concrete 5/18/2026 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/21/2026 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 5/27/2026 Corrections Issued JESUS PINEDA