751-753 N LOCKEARN ST 90049
Certificate Information: 751-753 N LOCKEARN ST 90049
- Application / Permit
- 25010-20000-04945
- Plan Check / Job No.
- B25VN30947
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY (66' X 53' IRREGULAR SHAPE) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 3/4/2026
- Issuing Office
- Current Status
- Issued on 3/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2025 | VAHAN JIVALAGIAN |
| Assigned to Zoning Architect | 10/23/2025 | AMIR NAKHLA |
| Corrections Issued | 10/25/2025 | VAHAN JIVALAGIAN |
| Quality Review Completed | 10/28/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 10/28/2025 | APPLICANT |
| Applicant returned to address corrections | 12/9/2025 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 12/17/2025 | VAHAN JIVALAGIAN |
| Plan Check Approved | 3/4/2026 | VAHAN JIVALAGIAN |
| Issued | 3/4/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | CINDY QI |
| Permit | Cleared | 11/13/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 11/13/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 11/18/2025 | JOHN CONNEALLY |
| Sewer availability | Cleared | 11/18/2025 | CINDY QI |
| Trees in Parkway | Cleared | 12/8/2025 | BRANDON WONG |
| GPI Written Notices | Cleared | 12/9/2025 | VAHAN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 12/9/2025 | VAHAN JIVALAGIAN |
| Zoning Plan Check | Cleared | 12/17/2025 | AMIR NAKHLA |
| Miscellaneous | Cleared | 1/27/2026 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/17/2026 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 4/2/2026 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 4/2/2026 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/8/2026 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 5/5/2026 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/5/2026 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 5/19/2026 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/19/2026 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 5/28/2026 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2026 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 5/28/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/28/2026 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/1/2026 | Corrections Issued | EVAN COOPER |
| Shower Pan | 6/8/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/11/2026 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 6/22/2026 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/26/2026 | Approved | EVAN COOPER |
| Green Building Rough | 6/26/2026 | Approved | EVAN COOPER |
| Insulation | 6/26/2026 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/26/2026 | Approved | EVAN COOPER |
| Drywall Nailing | 7/1/2026 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 7/1/2026 | Approved | EVAN COOPER |
| Drywall Nailing | 7/7/2026 | Approved | EVAN COOPER |