5836-5838 N BALCOM AVE 91316
Certificate Information: 5836-5838 N BALCOM AVE 91316
- Application / Permit
- 25010-20000-04896
- Plan Check / Job No.
- B25VN30682
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) Irregualr shape (47'-11" X 39'-3") Single family dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21 and (N) attached ADU per LAMC 12.22 A.33(c) and (e) Per WFPP. NFPA 13D Fire sprinkler throughout.
- Permit Issued
- Issued on 1/8/2026
- Issuing Office
- Current Status
- Issued on 1/8/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2025 | EDWARD MEHRABIAN |
| Assigned to Zoning Architect | 10/30/2025 | MELISSA QUINONES |
| Corrections Issued | 11/4/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 11/14/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 11/17/2025 | APPLICANT |
| Plan Check Approved | 1/8/2026 | MARVEL DELACRUZ |
| Issued | 1/8/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/6/2025 | ROSE STEIN-WENDT |
| Construction within easement | Cleared | 11/6/2025 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 11/6/2025 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2025 | ROSE STEIN-WENDT |
| Hydrant and Access approval | Cleared | 11/12/2025 | GILBERT URREA |
| Sewer availability | Cleared | 11/12/2025 | ROSE STEIN-WENDT |
| ZI | Cleared | 12/16/2025 | YINGSHI HUANG |
| Senate Bill 9 | Cleared | 12/24/2025 | YINGSHI HUANG |
| Zoning Plan Check | Cleared | 1/2/2026 | EDWARD MEHRABIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2026 | Partial Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 2/27/2026 | Corrections Issued | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 3/3/2026 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2026 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 3/16/2026 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 3/16/2026 | Corrections Issued | JON MCHUGH |
| Verify Sprinkler Sign Off | 3/16/2026 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 3/19/2026 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 3/24/2026 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2026 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 4/9/2026 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 4/9/2026 | Not Ready for Inspection | JON MCHUGH |
| Deputy Drilled-In Anchors | 4/27/2026 | Conditional Approval | JON MCHUGH |
| Sewer | 5/12/2026 | Approved | HENRY KIM |
| Underground Mechanical | 5/12/2026 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 5/26/2026 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 5/26/2026 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 5/26/2026 | Approved | JON MCHUGH |