8052 N RHODES AVE 91605
Certificate Information: 8052 N RHODES AVE 91605
- Application / Permit
- 25010-20000-04799
- Plan Check / Job No.
- B25VN30176
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD PER SB9, NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/13/2026
- Issuing Office
- Current Status
- CofO in Progress on 6/8/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2025 | RARES BODEA |
| Assigned to Zoning Architect | 10/23/2025 | HAYDON CHAN |
| Corrections Issued | 10/31/2025 | RARES BODEA |
| Quality Review Completed | 11/6/2025 | STEVEN KIM |
| Building Plans Picked Up | 11/7/2025 | APPLICANT |
| Plan Check Approved | 1/13/2026 | RARES BODEA |
| Issued | 1/13/2026 | APPLICANT |
| CofO in Progress | 6/8/2026 | MATTHEW NELSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 11/4/2025 | SAFA JAVANMARDI |
| CPC | Cleared | 11/18/2025 | MATHEW QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 11/18/2025 | SAFA JAVANMARDI |
| Supp. Use District POD/CDO/TDO | Cleared | 11/18/2025 | MATHEW QUAN |
| Hydrant and Access approval | Cleared | 11/20/2025 | GILBERT URREA |
| Senate Bill 9 | Cleared | 11/24/2025 | RUBEN VASQUEZ |
| Construction within easement | Cleared | 12/4/2025 | GEVORK KARAPETYAN |
| Zoning Plan Check | Cleared | 1/6/2026 | HAYDON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/23/2026 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 1/29/2026 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Wood Construction | 3/11/2026 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 3/17/2026 | Conditional Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/17/2026 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/17/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/17/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/17/2026 | Approved | MATTHEW NELSON |
| Underground Mechanical | 3/17/2026 | Partial Approval | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 3/17/2026 | Approved | MATTHEW NELSON |
| Wood Frame | 3/17/2026 | Partial Approval | MATTHEW NELSON |
| Insulation | 3/20/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/20/2026 | Approved | MATTHEW NELSON |
| Shower Pan | 3/24/2026 | Approved | MATTHEW NELSON |
| Underground Mechanical | 3/24/2026 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/2/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/2/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/26/2026 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/26/2026 | No Access for Inspection | MATTHEW NELSON |
| Final | 5/26/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/26/2026 | Approved | MATTHEW NELSON |
| Green Building Final | 5/26/2026 | Approved | MATTHEW NELSON |
| HVAC-Final | 5/26/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/26/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Not Required | MATTHEW NELSON |
| Service/Power Release | 5/26/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 5/26/2026 | Approved | MATTHEW NELSON |
| Final | 6/1/2026 | Partial Approval | MATTHEW NELSON |
| Service/Power Release | 6/1/2026 | Approved | MATTHEW NELSON |
| Final | 6/8/2026 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 6/8/2026 | Approved | MATTHEW NELSON |