7342 N FORBES AVE 91406

Certificate Information: 7342 N FORBES AVE 91406

Application / Permit
25010-20000-04791
Plan Check / Job No.
B25VN30105
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY (35' X 29' IRR SHAPE) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 11/3/2025
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2025 APPLICANT
Assigned to Plan Check Engineer 10/16/2025 VAHAN JIVALAGIAN
Assigned to Zoning Architect 10/16/2025 MELISSA QUINONES
Corrections Issued 10/20/2025 VAHAN JIVALAGIAN
Quality Review Completed 10/20/2025 OMID HEDAYAT
Building Plans Picked Up 10/21/2025 APPLICANT
Plan Check Approved 11/3/2025 VAHAN JIVALAGIAN
Issued 11/3/2025 APPLICANT
CofO in Progress 4/2/2026 KIRK SANDERS
Permit Finaled 5/14/2026 RUBEN SALAS
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/22/2025 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 10/22/2025 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 10/23/2025 MARKOS PEREZ-BRAN
Sewer availability Cleared 10/23/2025 MARKOS PEREZ-BRAN
Zoning Plan Check Cleared 10/30/2025 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/20/2025 Partial Approval KEVIN BERBERYAN
PLUMBING-Rough 11/20/2025 Partial Approval KEVIN BERBERYAN
Footing/Foundation/Slab 11/25/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Conditional Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/26/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 12/26/2025 Corrections Issued NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 12/26/2025 Partial Approval NICHOLAS TROWBRIDGE
PLUMBING-Rough 12/26/2025 Approved NICHOLAS TROWBRIDGE
Wood Frame 12/26/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 12/29/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/29/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 12/29/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 12/29/2025 Approved GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 12/29/2025 Approved GAREN HAYRAPETYAN
Insulation 12/31/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 1/5/2026 Approved GAREN HAYRAPETYAN
Insulation 1/5/2026 Approved GAREN HAYRAPETYAN
Shower Pan 1/5/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/8/2026 Approved CRAIG DAVIS
Sewer 2/25/2026 Approved MICHAEL CORTEZ
Underground Mechanical 2/25/2026 Partial Approval MICHAEL CORTEZ
Underground Mechanical 3/2/2026 Approved KIRK SANDERS
ELECTRICAL-Final 3/27/2026 Approved KEVIN BERBERYAN
Final 3/27/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 3/27/2026 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 3/27/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 3/27/2026 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV No Gas KEVIN BERBERYAN
Service/Power Release 3/27/2026 Approved KEVIN BERBERYAN
Smoke Detectors 3/27/2026 Approved KEVIN BERBERYAN
Final 4/1/2026 OK to Issue CofO KIRK SANDERS
Green Building Final 4/1/2026 Approved KIRK SANDERS