18567 W RAYEN ST 91324
Certificate Information: 18567 W RAYEN ST 91324
- Application / Permit
- 25010-20000-04729
- Plan Check / Job No.
- B25VN29809
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER GC 66323(a)(4) (ADU UNIT#2) (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 3/16/2026
- Issuing Office
- Valley
- Current Status
- Issued on 3/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/9/2025 | APPLICANT |
| Assigned to Zoning Architect | 10/16/2025 | LY CHEA |
| Assigned to Plan Check Engineer | 10/23/2025 | EDWARD MEHRABIAN |
| Corrections Issued | 10/28/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 11/4/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 11/21/2025 | APPLICANT |
| Plan Check Approved | 3/12/2026 | NILOOFAR MEHRAIN |
| Issued | 3/16/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 11/3/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2025 | CINDY QI |
| Sewer availability | Cleared | 11/5/2025 | CINDY QI |
| Trees in Parkway | Cleared | 1/15/2026 | RICHARD SANCHEZ |
| Construction near power lines | Cleared | 2/6/2026 | GEVORK KARAPETYAN |
| Permit | Cleared | 2/6/2026 | LEE GUILBEAUX |
| Zoning Plan Check | Cleared | 3/2/2026 | LY CHEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Underground Mechanical | 6/8/2026 |
| PLUMBING-Rough | 6/8/2026 |
Inspection Request History
| PLUMBING-Rough | 4/10/2026 | Partial Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 4/16/2026 | Approved | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 4/17/2026 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 5/1/2026 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2026 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2026 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2026 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 6/2/2026 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 6/2/2026 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 6/2/2026 | Corrections Issued | JACK KARGODORIAN |