6559 N BEN AVE 91606

Certificate Information: 6559 N BEN AVE 91606

Application / Permit
25010-20000-04720
Plan Check / Job No.
B25VN27483
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
EPLAN: ADD 2ND FLOOR AND CONVERSION OF DEN TO ACCESSORY DWELLING UNIT AS PER , LAMC 12.22 A.33 (c) and (e) , ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/2/2026
Issuing Office
Current Status
Issued on 6/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/25/2025 APPLICANT
Assigned to Plan Check Engineer 10/2/2025 RARES BODEA
Assigned to Zoning Architect 10/2/2025 SAAD LADHANI
Corrections Issued 10/8/2025 RARES BODEA
Quality Review Completed 10/16/2025 STEVEN KIM
Applicant returned to address corrections 3/20/2026 RARES BODEA
Applicant returned to address corrections 4/14/2026 RARES BODEA
Applicant returned to address corrections 4/28/2026 RARES BODEA
Plan Check Approved 5/18/2026 RARES BODEA
No Progress 5/18/2026 RARES BODEA
Plan Check Approved 5/19/2026 RARES BODEA
Issued 6/2/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/5/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/5/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/30/2026 DERRICK MAGEE
Sewer availability Cleared 1/30/2026 DERRICK MAGEE
Zoning Plan Check Cleared 3/12/2026 SAAD LADHANI

Contact Information

Contractor Amin Farahpour; Lic. No.: 1079005-B       ,
Engineer Danialian,, Derik; Lic. No.: C94256 15904 INDEX ST.      GRANADA HILLS, CA 91344

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

HVAC-Rough 7/31/2026    Time Frame: 10-12
Floor/Roof Diaphrgm/Shear Wall 7/31/2026    Time Frame: 10-12
ELECTRICAL-Rough 7/31/2026    Time Frame: 10-12
Deputy Wood Construction 7/31/2026   
Floor/Roof Diaphrgm/Shear Wall 8/4/2026   
ELECTRICAL-Rough 8/4/2026   
PLUMBING-Rough 8/4/2026   
HVAC-Rough 8/4/2026   

Inspection Request History

Footing/Foundation/Slab 6/24/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/25/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 6/29/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 7/1/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/1/2026 Approved ROBERTO PALACIOS-LOPEZ