1950 1/2-3/4 S CORNING ST 90034

Certificate Information: 1950 1/2-3/4 S CORNING ST 90034

Application / Permit
25010-20000-04701
Plan Check / Job No.
B25VN29639
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) TWO UNITS (35' X 30'-8") DET ADUS PER GC 66323(a)(4).
Permit Issued
Issued on 12/31/2025
Issuing Office
West Los Angeles
Current Status
Issued on 12/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/8/2025 APPLICANT
Assigned to Plan Check Engineer 10/9/2025 EDWARD MEHRABIAN
Assigned to Zoning Architect 10/9/2025 ALIZA NAZIR
Corrections Issued 10/12/2025 EDWARD MEHRABIAN
Quality Review Completed 10/20/2025 OMID HEDAYAT
Building Plans Picked Up 10/20/2025 APPLICANT
Plan Check Approved 11/5/2025 EDWARD MEHRABIAN
Issued 12/31/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/21/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 10/21/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 10/21/2025 MICHAEL BROWN
Sewer availability Cleared 10/21/2025 MICHAEL BROWN
Zoning Plan Check Cleared 10/29/2025 ALIZA NAZIR

Contact Information

Architect Nigosian,, Michael Nickolas; Lic. No.: C35308 75-572 PAINTED DESERT DRIVE      INDIAN WELLS, CA 92210
Contractor Polestar Builders Group Inc; Lic. No.: 1122144-B 20337 MOBILE ST      WINNETKA, CA 91306
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/26/2026 Approved MICHAEL ALLEN
Footing/Foundation/Slab 2/5/2026 Approved WILBER ROSALES
Wood Frame 2/24/2026 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 3/3/2026 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Not Ready for Inspection WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Partial Approval WILBER ROSALES
PLUMBING-Rough 4/2/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 4/7/2026 Partial Approval RYAN SALAZAR
HVAC-Rough 4/8/2026 Approved WILBER ROSALES
Shower Pan 4/9/2026 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 4/13/2026 Approved WILBER ROSALES
BUILDING-Rough-Frame 4/16/2026 Partial Approval WILBER ROSALES
Green Building Rough 4/16/2026 Approved WILBER ROSALES
Insulation 4/16/2026 Partial Approval WILBER ROSALES
Verify Sprinkler Sign Off 4/16/2026 Approved WILBER ROSALES
Insulation 4/24/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 4/24/2026 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 4/30/2026 Approved WILBER ROSALES
Drywall Nailing 5/7/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 5/7/2026 Approved WILBER ROSALES
Sewer 5/26/2026 Partial Approval WILBER ROSALES
Underground Mechanical 5/26/2026 Partial Approval WILBER ROSALES
Sewer 6/4/2026 Approved WILBER ROSALES