17422 W CHASE ST 91325
Certificate Information: 17422 W CHASE ST 91325
- Application / Permit
- 25010-20000-04696
- Plan Check / Job No.
- B25VN20754
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW DETACHED ADU PER STATE LAW (ADU#2). WORK DONE PER ENGINEER DESIGN **13D SPRINKLER REQUIRED** 3 OF 3
- Permit Issued
- Issued on 12/1/2025
- Issuing Office
- Current Status
- Issued on 12/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2025 | KHUONG TRUONG |
| Assigned to Zoning Architect | 7/24/2025 | CAMERON JONES |
| Corrections Issued | 7/28/2025 | KHUONG TRUONG |
| Quality Review Completed | 7/30/2025 | GARO TELMI |
| Applicant returned to address corrections | 9/4/2025 | KHUONG TRUONG |
| Applicant returned to address corrections | 9/18/2025 | KHUONG TRUONG |
| Plan Check Approved | 11/6/2025 | KHUONG TRUONG |
| Issued | 12/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2025 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2025 | JEREMY CHOK |
| Low Impact Development (LID) | Cleared | 10/15/2025 | ERNEST TSE |
| Public Works-Highway Ded. | Cleared | 10/15/2025 | KHUONG TRUONG |
| Roof/Waste drainage to street | Cleared | 10/15/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 10/15/2025 | JEREMY CHOK |
| Zoning Plan Check | Cleared | 10/31/2025 | CAMERON JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: NA38454 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/19/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Sewer | 5/19/2026 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 5/19/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 5/28/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 6/1/2026 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 6/1/2026 | Approved | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 6/5/2026 | Approved | CHRISTOPHER ROJAS |