7827 N VICKY AVE 91304

Certificate Information: 7827 N VICKY AVE 91304

Application / Permit
25010-20000-04652
Plan Check / Job No.
B25VN29430
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: NEW 2-STORY (30' X 21'-5") ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 12/31/2025
Issuing Office
Current Status
Issued on 12/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/6/2025 APPLICANT
Assigned to Plan Check Engineer 10/16/2025 VAHAN JIVALAGIAN
Assigned to Zoning Architect 10/16/2025 MANUEL ZAVALETA
Corrections Issued 10/18/2025 VAHAN JIVALAGIAN
Quality Review Completed 10/23/2025 OMID HEDAYAT
Plan Check Approved 12/29/2025 VAHAN JIVALAGIAN
Issued 12/31/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 12/4/2025 GEVORK KARAPETYAN
Construction within easement Cleared 12/4/2025 GEVORK KARAPETYAN
Address approval Cleared 12/5/2025 JESUS LUNA
Eng Process Fee Ord 176,300 Cleared 12/5/2025 JESUS LUNA
Sewer availability Cleared 12/5/2025 JESUS LUNA
Roof/Waste drainage to street Cleared 12/10/2025 JESUS LUNA
Zoning Plan Check Cleared 12/18/2025 Aung Soe

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/14/2026 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 1/21/2026 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/30/2026 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/2/2026 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 3/10/2026 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 3/10/2026 Partial Approval JEFFREY HARTLINE
HVAC-Rough 3/10/2026 Approved JEFFREY HARTLINE
PLUMBING-Rough 3/10/2026 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 3/16/2026 Approved HENRY KIM
Green Building Rough 3/16/2026 Approved HENRY KIM
Interior/Exterior Lathing 3/16/2026 Partial Approval HENRY KIM
Special/Order Compliance 3/16/2026 Corrections Issued HENRY KIM
Insulation 3/20/2026 Approved JEFFREY HARTLINE
Drywall Nailing 3/27/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 4/1/2026 Partial Approval JEFFREY HARTLINE
Shower Pan 4/1/2026 Approved JEFFREY HARTLINE
Underground Mechanical 4/16/2026 Approved JEFFREY HARTLINE
Underground Mechanical 4/22/2026 Approved JEFFREY HARTLINE
Underground Mechanical 5/4/2026 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 5/21/2026 Not Ready for Inspection TROY SANDERS