956 N LINDA FLORA DR 90049

Certificate Information: 956 N LINDA FLORA DR 90049

Application / Permit
25010-20000-04645
Plan Check / Job No.
B25VN29375
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 80'-10" X 115'-10" IRREGULAR SHAPED 2-STORY SFD OVER BASEMENT WITH 2-CAR GARAGE AND PATIO COVER. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/16/2025
Issuing Office
Current Status
Issued on 12/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/6/2025 APPLICANT
Assigned to Plan Check Engineer 10/9/2025 RAPHAEL ROSAS
Assigned to Zoning Architect 10/9/2025 LY CHEA
Corrections Issued 10/14/2025 RAPHAEL ROSAS
Quality Review Completed 10/17/2025 STEVEN KIM
Building Plans Picked Up 10/21/2025 APPLICANT
Applicant returned to address corrections 11/12/2025 RAPHAEL ROSAS
Plan Check Approved 12/1/2025 RAPHAEL ROSAS
Issued 12/16/2025 APPLICANT

Permit Application Clearance Information

CPC Cleared 10/20/2025 JAZMIN ROQUE
CPC Cleared 10/20/2025 JAZMIN ROQUE
CPC Cleared 10/20/2025 JAZMIN ROQUE
ZI Cleared 10/20/2025 JAZMIN ROQUE
Address approval Cleared 10/23/2025 MICHAEL BROWN
BHO/Hillside ordinance Cleared 10/23/2025 MICHAEL BROWN
BHO/Hillside ordinance Cleared 10/23/2025 MICHAEL BROWN
BHO/Hillside ordinance Cleared 10/23/2025 MICHAEL BROWN
BHO/Hillside ordinance Cleared 10/23/2025 MICHAEL BROWN
BHO/Hillside ordinance Cleared 10/23/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 10/23/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 10/23/2025 MICHAEL BROWN
Sewer availability Cleared 10/23/2025 MICHAEL BROWN
Distance to fire station Cleared 10/25/2025 RUEL COLE
Hydrant and Access approval Cleared 10/25/2025 RUEL COLE
Low Impact Development (LID) Cleared 10/27/2025 ERNEST TSE
Excavation more than 5-ft deep Cleared 11/12/2025 CALOSHA APPROVED
GPI Written Notices Cleared 11/12/2025 RAPHAEL ROSAS
Zoning Plan Check Cleared 11/20/2025 LY CHEA
Grading Pre-Inspection Cleared 12/1/2025 RAPHAEL ROSAS

Contact Information

Contractor Romm Builders Inc; Lic. No.: 779702-B 5746 RHODES AVE      VALLEY VILLAGE, CA 91607
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Floor/Roof Diaphrgm/Shear Wall 7/29/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2026 Partial Approval EVAN COOPER
Piling/Pier/Caisson 2/5/2026 Partial Approval EVAN COOPER
Service/Power Release 2/12/2026 Approved EVAN COOPER
Deputy Reinf. Concrete 2/23/2026 Conditional Approval EVAN COOPER
Deputy Reinf. Concrete 2/24/2026 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 2/24/2026 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 3/3/2026 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 3/3/2026 Partial Approval EVAN COOPER
PLUMBING-Rough 3/4/2026 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/4/2026 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/5/2026 Conditional Approval ANDREW NAVE
Sewer 3/17/2026 Not Ready for Inspection EVAN COOPER
Underground Mechanical 3/17/2026 Partial Approval EVAN COOPER
Footing/Foundation/Slab 3/26/2026 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 3/31/2026 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 4/10/2026 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 4/16/2026 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 4/16/2026 Partial Approval RYAN SALAZAR
Deputy Reinf. Concrete 4/17/2026 Conditional Approval ANDREW NAVE
Pre-Gunite 5/13/2026 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 5/27/2026 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 6/4/2026 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 6/4/2026 Partial Approval RYAN SALAZAR
Deputy Reinf. Concrete 6/5/2026 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/6/2026 Partial Approval DAVID SCANTLIN