13676 W PAXTON ST 91331

Certificate Information: 13676 W PAXTON ST 91331

Application / Permit
25010-20000-04643
Plan Check / Job No.
B25VN29362
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ADU PER 12.22 A.33(b)(1)
Permit Issued
Issued on 2/1/2026
Issuing Office
Current Status
Issued on 2/1/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/7/2025 APPLICANT
Assigned to Plan Check Engineer 10/16/2025 ZENA HADDIS
Assigned to Zoning Architect 10/16/2025 LINGHUI YU
Corrections Issued 10/30/2025 ZENA HADDIS
Quality Review Completed 11/4/2025 CHIHARU SUZUKI
Plan Check Approved 1/30/2026 ZENA HADDIS
Plan Check Approved 1/30/2026 ZENA HADDIS
Issued 2/1/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/19/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 12/8/2025 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 12/19/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/23/2025 BIAINA HARITUNIAN
Sewer availability Cleared 12/23/2025 BIAINA HARITUNIAN
Zoning Plan Check Cleared 1/6/2026 LINGHUI YU

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Insulation 6/22/2026   
Interior/Exterior Lathing 6/22/2026   

Inspection Request History

Pre-Inspection 2/3/2026 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 3/20/2026 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 4/3/2026 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 4/28/2026 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 5/20/2026 Approved MICHEL ABAJAN
Green Building Rough 5/20/2026 Approved MICHEL ABAJAN
MERV13>=Rough 5/20/2026 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 5/20/2026 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 5/20/2026 Approved MICHEL ABAJAN