762-764 E 78TH ST 90001

Certificate Information: 762-764 E 78TH ST 90001

Application / Permit
25010-20000-04617
Plan Check / Job No.
B25VN27504
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNITS PER GC 66323(a)(4) WITH ATTACHED GARAGE. **NFPA-13D FIRE SPRINKLERS TO BE INSTALLED THROUGHOUT**
Permit Issued
Issued on 2/13/2026
Issuing Office
Current Status
Issued on 2/13/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/19/2025 APPLICANT
Assigned to Zoning Architect 9/25/2025 KRISTEL MARQUEZ
Assigned to Plan Check Engineer 9/25/2025 SELLA BENYAMIN
Corrections Issued 10/7/2025 SELLA BENYAMIN
Quality Review Completed 10/14/2025 CHIHARU SUZUKI
Applicant returned to address corrections 2/2/2026 MIROOSH KHACHATOORIAN
Plan Check Approved 2/3/2026 MIROOSH KHACHATOORIAN
No Progress 2/3/2026 MIROOSH KHACHATOORIAN
Plan Check Approved 2/3/2026 MIROOSH KHACHATOORIAN
Issued 2/13/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/10/2025 ROSE STEIN-WENDT
Sewer availability Cleared 10/10/2025 ROSE STEIN-WENDT
Eng Process Fee Ord 176,300 Cleared 11/5/2025 ROSE STEIN-WENDT
Roof/Waste drainage to street Cleared 11/14/2025 ROSE STEIN-WENDT
DAS Clearance Cleared 1/6/2026 NORLITO MEDRANO
Zoning Plan Check Cleared 1/20/2026 CHIHARU SUZUKI

Contact Information

Contractor Golden Point Construction; Lic. No.: 965193-B       ,
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Rough-Elec/Plmb/HVAC 7/21/2026    Time Frame: 10-12
HVAC-Rough 7/24/2026   
PLUMBING-Rough 7/24/2026   
ELECTRICAL-Rough 7/24/2026   

Inspection Request History

PLUMBING-Rough 3/5/2026 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 3/9/2026 Approved JOHN QUINTANILLA
Underground Mechanical 3/9/2026 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 3/19/2026 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 4/10/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 5/7/2026 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Corrections Issued JOHN QUINTANILLA
Deputy Wood Construction 5/27/2026 Conditional Approval BRIAN SULLIVAN
HVAC-Rough 6/4/2026 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 6/9/2026 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 6/18/2026 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 6/26/2026 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 6/26/2026 Partial Inspection RAUL BARAJAS
Green Building Rough 6/26/2026 Partial Inspection RAUL BARAJAS
HVAC-Rough 6/26/2026 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 6/26/2026 Partial Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 6/26/2026 Approved RAUL BARAJAS
BUILDING-Rough-Frame 7/1/2026 Partial Approval LUIS CASTRO
Green Building Rough 7/1/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 7/1/2026 Partial Approval LUIS CASTRO
Drywall Nailing 7/17/2026 Corrections Issued SALVADOR MARTINEZ