646-646 1/2 W 30TH ST 90007

Certificate Information: 646-646 1/2 W 30TH ST 90007

Application / Permit
25010-20000-04558
Plan Check / Job No.
B25VN28976
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY (38' X 22'-7") ACCESSORY BUILDING WITH 2 ADUS PER GC 66323(a)(4). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 1/14/2026
Issuing Office
Metro
Current Status
Issued on 1/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/1/2025 APPLICANT
Assigned to Plan Check Engineer 10/2/2025 VAHAN JIVALAGIAN
Assigned to Zoning Architect 10/2/2025 AMIR NAKHLA
Corrections Issued 10/5/2025 VAHAN JIVALAGIAN
Quality Review Completed 10/9/2025 OMID HEDAYAT
Building Plans Picked Up 10/15/2025 APPLICANT
Disabled Access Plans Picked Up 10/15/2025 APPLICANT
Applicant returned to address corrections 1/8/2026 VAHAN JIVALAGIAN
Plan Check Approved 1/12/2026 VAHAN JIVALAGIAN
Issued 1/14/2026 APPLICANT

Permit Application Clearance Information

DAS Clearance Cleared 10/7/2025 NORLITO MEDRANO
Address approval Cleared 10/21/2025 JEREMY CHOK
Low Impact Development (LID) Cleared 10/23/2025 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 10/24/2025 JEREMY CHOK
Roof/Waste drainage to street Cleared 10/24/2025 TERRY PHAN
Sewer availability Cleared 10/24/2025 JEREMY CHOK
Frnt yard landscape/Water mgmt Cleared 11/21/2025 JASON CHAN
Historic Resource Verification Cleared 11/24/2025 YASMINE BASHIRI
Redevelopment Project Area Cleared 11/24/2025 YASMINE BASHIRI
Highway dedication Cleared 12/24/2025 DIANA RENTERIA
Zoning Plan Check Cleared 1/6/2026 AMIR NAKHLA
Hold Cleared 5/27/2026 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/5/2026 Partial Approval ALEJANDRO DE ARTOLA
METHANE-Rough 6/5/2026 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 6/5/2026 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 6/8/2026 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Subgrade 6/9/2026 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Barrier 7/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Subgrade 7/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 7/21/2026 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/21/2026 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Barrier 7/21/2026 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 7/21/2026 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/22/2026 Approved ALEJANDRO DE ARTOLA