851-853 S MALCOLM AVE 90024

Certificate Information: 851-853 S MALCOLM AVE 90024

Application / Permit
25010-20000-04512
Plan Check / Job No.
B25VN28703
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY (71' X 43'-6" IRREGULAR SHAPE) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e). NFPA 13R FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 12/17/2025
Issuing Office
Current Status
Issued on 12/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/30/2025 APPLICANT
Assigned to Plan Check Engineer 10/2/2025 VAHAN JIVALAGIAN
Assigned to Zoning Architect 10/2/2025 RYAN DEL POSO
Corrections Issued 10/7/2025 VAHAN JIVALAGIAN
Quality Review Completed 10/9/2025 OMID HEDAYAT
Building Plans Picked Up 10/15/2025 APPLICANT
Applicant returned to address corrections 12/9/2025 VAHAN JIVALAGIAN
Plan Check Approved 12/17/2025 VAHAN JIVALAGIAN
Issued 12/17/2025 APPLICANT

Permit Application Clearance Information

Historic monument Cleared 10/27/2025 LAMBERT GIESSINGER
CPC Cleared 10/31/2025 YINGSHI HUANG
Address approval Cleared 11/3/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/3/2025 BIAINA HARITUNIAN
Miscellaneous Cleared 11/3/2025 BIAINA HARITUNIAN
Sewer availability Cleared 11/3/2025 BIAINA HARITUNIAN
Trees in Parkway Cleared 11/20/2025 RICHARD SANCHEZ
Permit Cleared 11/26/2025 ABEL CASILLAS
Roof/Waste drainage to street Cleared 11/26/2025 ABEL CASILLAS
Hydrant and Access approval Cleared 12/2/2025 PATRICK PEREZ
Specific Plan Cleared 12/8/2025 PEDRO AYALA
Zoning Plan Check Cleared 12/12/2025 VAHAN JIVALAGIAN
GPI Written Notices Cleared 12/17/2025 VAHAN JIVALAGIAN
Grading Pre-Inspection Cleared 12/17/2025 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/20/2026 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/21/2026 Partial Approval EVAN COOPER
PLUMBING-Rough 1/21/2026 Partial Approval EVAN COOPER
Sewer 1/21/2026 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 1/23/2026 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 1/30/2026 Approved RYAN SALAZAR
Deputy Wood Construction 2/17/2026 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/20/2026 Partial Approval RYAN SALAZAR
Deputy Wood Construction 3/12/2026 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 3/13/2026 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 3/31/2026 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 3/31/2026 Approved RYAN SALAZAR
PLUMBING-Rough 3/31/2026 Conditional Approval RYAN SALAZAR
Verify Sprinkler Sign Off 3/31/2026 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 4/13/2026 Partial Approval RYAN SALAZAR
Shower Pan 4/13/2026 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/23/2026 Approved RYAN SALAZAR
ELECTRICAL-Rough 4/23/2026 Approved RYAN SALAZAR
Green Building Rough 4/23/2026 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/23/2026 Partial Approval RYAN SALAZAR
Verify Sprinkler Sign Off 4/23/2026 Approved RYAN SALAZAR
Wood Frame 4/23/2026 Approved RYAN SALAZAR
Drywall Nailing 5/1/2026 Approved CHRISTOPHER WILSON
Final 5/1/2026 Corrections Issued CHRISTOPHER WILSON
Insulation 5/1/2026 Approved CHRISTOPHER WILSON
Special/Order Compliance 5/27/2026 Approved ANDREW NAVE