7605 1/2 N GREG AVE 91352
Certificate Information: 7605 1/2 N GREG AVE 91352
- Application / Permit
- 25010-20000-04481
- Plan Check / Job No.
- B25VN28573
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY (32'-9" X 21'-5") ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/18/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2025 | VAHAN JIVALAGIAN |
| Assigned to Zoning Architect | 10/2/2025 | LY CHEA |
| Corrections Issued | 10/9/2025 | VAHAN JIVALAGIAN |
| Quality Review Completed | 10/10/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 10/14/2025 | APPLICANT |
| Plan Check Approved | 11/3/2025 | VAHAN JIVALAGIAN |
| Issued | 11/3/2025 | APPLICANT |
| CofO in Progress | 5/18/2026 | DAVID ANDERSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2025 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 10/14/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 10/15/2025 | TREVOR QUAN |
| Zoning Plan Check | Cleared | 11/3/2025 | LY CHEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/5/2025 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/5/2025 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 11/5/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 11/17/2025 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 11/19/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 12/29/2025 | Approved | JACK KARGODORIAN |
| Pre-Inspection | 1/5/2026 | Partial Inspection | DAVID ANDERSON |
| Shower Pan | 1/5/2026 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/20/2026 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 1/20/2026 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 1/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 1/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 1/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/2/2026 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 2/2/2026 | Approved | DAVID ANDERSON |
| Insulation | 2/20/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/23/2026 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 3/5/2026 | Approved | DAVID ANDERSON |
| Underground Mechanical | 3/17/2026 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Final | 4/29/2026 | Corrections Issued | DAVID ANDERSON |
| Final | 5/6/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 5/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Not Ready | DAVID ANDERSON |
| Service/Power Release | 5/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 5/6/2026 | Approved | DAVID ANDERSON |
| Final | 5/13/2026 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 5/13/2026 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 5/13/2026 | Approved | DAVID ANDERSON |