1165 N MONUMENT ST 90272
Certificate Information: 1165 N MONUMENT ST 90272
- Application / Permit
- 25010-20000-04479
- Plan Check / Job No.
- B25VN28571
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ****2025 WILDFIRE EO-1 ELIGIBLE REBUILD**** NEW 2 STORY SFD WITH ATTACHED 2-CAR GARAGE AND ROOF DECK, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/21/2025
- Issuing Office
- Current Status
- Issued on 10/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2025 | RARES BODEA |
| Corrections Issued | 10/1/2025 | RARES BODEA |
| Quality Review Completed | 10/1/2025 | STEVEN KIM |
| Building Plans Picked Up | 10/1/2025 | APPLICANT |
| Applicant returned to address corrections | 10/9/2025 | RARES BODEA |
| Plan Check Approved | 10/20/2025 | RARES BODEA |
| Issued | 10/21/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/6/2025 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 10/7/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2025 | CELINA MORENO |
| Sewer availability | Cleared | 10/17/2025 | CELINA MORENO |
Contact Information
| Contractor | Ortam Construction Inc; Lic. No.: 880225-B | 4500 PARK GRANADA #202 CALABASAS, CA 91302 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 6/9/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/2/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/2/2025 | Partial Approval | TEMISTOCLES CAAL |
| Underground Mechanical | 12/2/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/8/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2026 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/3/2026 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2026 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 4/6/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 4/27/2026 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/6/2026 | Partial Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 5/6/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 5/6/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Wood Construction | 5/7/2026 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 5/14/2026 | Approved | JESUS PINEDA |
| Green Building Rough | 5/14/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/14/2026 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 5/28/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 5/28/2026 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 5/29/2026 | Approved | ARAM AVEDISIAN |
| Shower Pan | 6/3/2026 | Approved | TEMISTOCLES CAAL |