4333 N ELMER AVE 91602
Certificate Information: 4333 N ELMER AVE 91602
- Application / Permit
- 25010-20000-04461
- Plan Check / Job No.
- B25VN28471
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR SHAPED 38' x 69'-6" TWO-STORY SINGLE FAMILY DWELLING W/ ATT 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 2/25/2026
- Issuing Office
- Current Status
- Issued on 2/25/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2025 | SEAN SHAHMIRI |
| Assigned to Zoning Architect | 10/9/2025 | RYAN DEL POSO |
| Corrections Issued | 10/16/2025 | SEAN SHAHMIRI |
| Quality Review Completed | 10/28/2025 | STEVEN KIM |
| Plan Check Approved | 1/27/2026 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/30/2026 | SEAN SHAHMIRI |
| Issued | 2/25/2026 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 10/29/2025 | DALIA MOKAYED |
| Hydrant and Access approval | Cleared | 10/29/2025 | PATRICK PEREZ |
| ZI | Cleared | 11/3/2025 | DALIA MOKAYED |
| Address approval | Cleared | 11/19/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/19/2025 | BIAINA HARITUNIAN |
| Permit | Cleared | 12/11/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/30/2025 | BIAINA HARITUNIAN |
| Zoning Plan Check | Cleared | 1/23/2026 | RYAN DEL POSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 | 17770 CAPE JASMINE RD CANYON COUNTRY, CA 91387 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/3/2026 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 3/6/2026 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/6/2026 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 4/16/2026 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/20/2026 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2026 | Corrections Issued | JAVIER RAMOS JR |
| Sewer | 4/20/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/27/2026 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 4/27/2026 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/27/2026 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 4/27/2026 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/6/2026 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/6/2026 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/6/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/6/2026 | Partial Inspection | JAVIER RAMOS JR |
| MERV13>=Rough | 5/6/2026 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/6/2026 | Approved | JAVIER RAMOS JR |