10558 N DEBRA AVE 91344

Certificate Information: 10558 N DEBRA AVE 91344

Application / Permit
25010-20000-04398
Plan Check / Job No.
B25VN28038
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(b)(1) PER ENGINEERING
Permit Issued
Issued on 10/15/2025
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2025 APPLICANT
Assigned to Plan Check Engineer 9/25/2025 ALFRED RAMIREZ
Assigned to Zoning Architect 9/25/2025 LINGHUI YU
Corrections Issued 10/1/2025 ALFRED RAMIREZ
Quality Review Completed 10/1/2025 STEVEN KIM
Building Plans Picked Up 10/2/2025 APPLICANT
Plan Check Approved 10/15/2025 ALFRED RAMIREZ
Issued 10/15/2025 APPLICANT
CofO in Progress 3/16/2026 CHRISTOPHER ROJAS
CofO Issued 4/16/2026 RUBEN SALAS
Permit Finaled 4/16/2026 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 10/3/2025 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 10/3/2025 DAVID LOPEZ
Address approval Cleared 10/6/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 10/6/2025 DAVID LOPEZ
Sewer availability Cleared 10/6/2025 DAVID LOPEZ
Zoning Plan Check Cleared 10/14/2025 LINGHUI YU

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/5/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 11/5/2025 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 11/12/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/12/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 12/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 12/8/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/15/2025 Approved CRAIG DAVIS
HVAC-Rough 12/15/2025 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 12/15/2025 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 12/19/2025 Corrections Issued RAUL OLAGI
Green Building Rough 12/19/2025 Not Ready for Inspection RAUL OLAGI
Insulation 12/19/2025 Not Ready for Inspection RAUL OLAGI
Verify Sprinkler Sign Off 12/19/2025 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 12/24/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 12/24/2025 Approved CHRISTOPHER ROJAS
Insulation 12/24/2025 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 12/24/2025 Approved CHRISTOPHER ROJAS
Wood Frame 12/24/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 12/31/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 1/12/2026 Approved MICHAEL CORTEZ
Shower Pan 1/12/2026 Approved MICHAEL CORTEZ
ELECTRICAL-Final 3/10/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 3/10/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 3/10/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 3/10/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 3/10/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 3/10/2026 Approved CHRISTOPHER ROJAS
Final 3/13/2026 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 3/13/2026 Approved CHRISTOPHER ROJAS