10027 N NOBLE AVE 91345

Certificate Information: 10027 N NOBLE AVE 91345

Application / Permit
25010-20000-04371
Plan Check / Job No.
B25VN27882
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 50'-0" X 23'-3" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1) .
Permit Issued
Issued on 10/24/2025
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2025 APPLICANT
Assigned to Plan Check Engineer 9/29/2025 ARTIN ZARUKIAN
Corrections Issued 9/29/2025 ARTIN ZARUKIAN
Building Plans Picked Up 10/6/2025 APPLICANT
Plan Check Approved 10/24/2025 GIOVANNY CHAVEZ
Issued 10/24/2025 APPLICANT
CofO in Progress 3/2/2026 JENNIFER RABUCHIN
CofO Issued 3/26/2026 RUBEN SALAS
Permit Finaled 3/26/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/10/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 10/10/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 10/10/2025 TAL SHEMEN
Sewer availability Cleared 10/10/2025 TAL SHEMEN
Construction near power lines Cleared 10/21/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/31/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Underground Mechanical 10/31/2025 Partial Approval NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 11/5/2025 Corrections Issued JENNIFER RABUCHIN
Sewer 11/5/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/18/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 12/8/2025 Corrections Issued JENNIFER RABUCHIN
Gas Test 12/8/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 12/8/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 12/8/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/8/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 12/8/2025 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 12/8/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 12/10/2025 Corrections Issued JENNIFER RABUCHIN
Insulation 12/10/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 12/12/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/12/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 12/23/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 12/23/2025 Approved JENNIFER RABUCHIN
Shower Pan 12/23/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/29/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/23/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 2/23/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Final 2/23/2026 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 2/23/2026 Approved JENNIFER RABUCHIN
Green Building Final 2/23/2026 Approved JENNIFER RABUCHIN
HVAC-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/23/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 2/23/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/27/2026 Approved JENNIFER RABUCHIN
Final 2/27/2026 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 2/27/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/27/2026 Approved JENNIFER RABUCHIN
Service/Power Release 2/27/2026 Approved JENNIFER RABUCHIN