3229-3231 S BUTLER AVE 90066

Certificate Information: 3229-3231 S BUTLER AVE 90066

Application / Permit
25010-20000-04364
Plan Check / Job No.
B25VN27850
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING UNIT WITH ATTACHED TRELLIS, 2-CAR GARAGE, AND ATTACHED 1-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c) and (e). NFPA-13D FIRE SPRINKLER THRU-OUT.
Permit Issued
Issued on 11/13/2025
Issuing Office
Current Status
Issued on 11/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/22/2025 APPLICANT
Assigned to Plan Check Engineer 9/25/2025 ALFRED RAMIREZ
Assigned to Zoning Architect 9/25/2025 SAAD LADHANI
Corrections Issued 9/30/2025 ALFRED RAMIREZ
Quality Review Completed 10/2/2025 STEVEN KIM
Building Plans Picked Up 10/3/2025 APPLICANT
Plan Check Approved 11/13/2025 ALFRED RAMIREZ
Issued 11/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/13/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/14/2025 LEE GUILBEAUX
Sewer availability Cleared 10/14/2025 LEE GUILBEAUX
Hydrant and Access approval Cleared 10/15/2025 GILBERT URREA
Low Impact Development (LID) Cleared 10/15/2025 ERNEST TSE
CPC Cleared 10/28/2025 ANGELA WILLIAMS
CPC Cleared 10/28/2025 ANGELA WILLIAMS
Roof/Waste drainage to street Cleared 10/28/2025 CARLOS AGUILERA
Specific Plan Cleared 10/29/2025 RICHARD WOO
Trees in Parkway Cleared 10/29/2025 MIGUEL ORNELAS
Permit Cleared 10/30/2025 CARLOS AGUILERA
Zoning Plan Check Cleared 11/6/2025 SAAD LADHANI
GPI Written Notices Cleared 11/13/2025 ALFRED RAMIREZ
Grading Pre-Inspection Cleared 11/13/2025 ALFRED RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/22/2026 Partial Approval ARAM AVEDISIAN
Sewer 1/22/2026 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 1/29/2026 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2026 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 3/31/2026 Approved RUBEN RIVAS
HVAC-Rough 3/31/2026 Approved RUBEN RIVAS
PLUMBING-Rough 3/31/2026 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/23/2026 Conditional Approval EUGENE CASSIDY
Green Building Rough 4/23/2026 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/23/2026 Partial Approval EUGENE CASSIDY
Shower Pan 4/23/2026 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 4/23/2026 Not Ready for Inspection EUGENE CASSIDY
Insulation 4/30/2026 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 4/30/2026 Partial Approval ANTHONY EGSON
Drywall Nailing 5/11/2026 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 5/11/2026 Approved EUGENE CASSIDY
Drywall Nailing 5/13/2026 Approved KIRK SANDERS
Special/Order Compliance 6/22/2026 Corrections Issued BOBBY KEY