332 N BEIRUT AVE 90272
Certificate Information: 332 N BEIRUT AVE 90272
- Application / Permit
- 25010-20000-04360
- Plan Check / Job No.
- B25VN27838
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, ROOF DECK (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/14/2025
- Issuing Office
- Current Status
- Issued on 10/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2025 | RAPHAEL ROSAS |
| Corrections Issued | 9/25/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 9/25/2025 | STEVEN KIM |
| Building Plans Picked Up | 9/29/2025 | APPLICANT |
| Plan Check Approved | 10/14/2025 | RAPHAEL ROSAS |
| Issued | 10/14/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 9/29/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 9/29/2025 | DERRICK MAGEE |
| Hydrant and Access approval | Cleared | 10/2/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Drywall Nailing | 6/8/2026 |
Inspection Request History
| PLUMBING-Rough | 11/4/2025 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 11/25/2025 | Partial Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 11/25/2025 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 2/3/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Conditional Approval | STEPHANIE SWANSON |
| Insulation | 4/7/2026 | Partial Inspection | HERBERT GIRON |
| PLUMBING-Rough | 4/7/2026 | Approved | HERBERT GIRON |
| Shower Pan | 4/7/2026 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 4/14/2026 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/21/2026 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/21/2026 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 5/4/2026 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/4/2026 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 5/4/2026 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 5/4/2026 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 5/4/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/7/2026 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/12/2026 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 5/12/2026 | Approved | STEPHANIE SWANSON |
| Insulation | 5/27/2026 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 6/4/2026 | Approved | STEPHANIE SWANSON |