9949 N NORWICH AVE 91345

Certificate Information: 9949 N NORWICH AVE 91345

Application / Permit
25010-20000-04289
Plan Check / Job No.
B25VN27307
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached ADU per LAMC 12.22 A33 (b)(1). Design per WFPP.
Permit Issued
Issued on 12/11/2025
Issuing Office
Current Status
Issued on 12/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/23/2025 APPLICANT
Assigned to Plan Check Engineer 9/26/2025 CAROLEAN BASMA
Corrections Issued 9/29/2025 CAROLEAN BASMA
Plan Check Approved 11/12/2025 CAROLEAN BASMA
Issued 12/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/15/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 10/15/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 10/17/2025 SAFA JAVANMARDI
Sewer availability Cleared 10/17/2025 SAFA JAVANMARDI
Construction near power lines Cleared 11/6/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/29/2026 Approved JENNIFER RABUCHIN
Sewer 3/12/2026 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 3/12/2026 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 4/6/2026 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/15/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/15/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/15/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Partial Approval JENNIFER RABUCHIN
Green Building Rough 4/21/2026 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 4/21/2026 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 4/21/2026 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/8/2026 Partial Approval JENNIFER RABUCHIN
Green Building Rough 5/8/2026 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/8/2026 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/2/2026 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/2/2026 Corrections Issued JENNIFER RABUCHIN
Gas Test 6/2/2026 Partial Approval JENNIFER RABUCHIN
Green Building Rough 6/2/2026 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 6/2/2026 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/2/2026 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/12/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/12/2026 Approved JENNIFER RABUCHIN
Green Building Rough 6/12/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/12/2026 Partial Approval JENNIFER RABUCHIN
Insulation 6/23/2026 Approved JENNIFER RABUCHIN
Shower Pan 7/2/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 7/8/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/8/2026 Approved JENNIFER RABUCHIN