520 W 57TH ST 90037

Certificate Information: 520 W 57TH ST 90037

Application / Permit
25010-20000-04271
Plan Check / Job No.
B25VN27146
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'-10" X 16'-8" DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
Permit Issued
Issued on 11/21/2025
Issuing Office
Valley
Current Status
Issued on 11/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/16/2025 APPLICANT
Assigned to Plan Check Engineer 9/19/2025 ARTIN ZARUKIAN
Corrections Issued 9/20/2025 ARTIN ZARUKIAN
Building Plans Picked Up 9/22/2025 APPLICANT
Applicant returned to address corrections 9/30/2025 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 10/3/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 11/21/2025 SAMUEL GONZALEZ
Issued 11/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/25/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 9/29/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 9/29/2025 MICHAEL BROWN
Sewer availability Cleared 9/29/2025 MICHAEL BROWN
Tenant Habitability Plan Cleared 10/1/2025 ARIC DEFUSCO
Construction near power lines Cleared 11/20/2025 RIDWAN HARDY

Contact Information

Contractor Pacific West Home Builders Inc; Lic. No.: 1111181-B 15910 VENTURA BLVD SUITE 1610      ENCINO, CA 91436
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/15/2026 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 1/20/2026 Approved SABAS ALONSO
Underground Mechanical 1/20/2026 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 2/2/2026 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/2/2026 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Approved LUIS CASTRO
HVAC-Rough 2/3/2026 Partial Approval LUIS CASTRO
PLUMBING-Rough 2/3/2026 Approved LUIS CASTRO
ELECTRICAL-Rough 2/4/2026 Approved SABAS ALONSO
HVAC-Rough 2/4/2026 Corrections Issued SABAS ALONSO
Wood Frame 2/4/2026 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 2/9/2026 Approved SABAS ALONSO
Green Building Rough 2/9/2026 Approved SABAS ALONSO
HVAC-Rough 2/9/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 2/9/2026 Corrections Issued SABAS ALONSO
Insulation 2/11/2026 Approved SABAS ALONSO
Shower Pan 2/11/2026 Approved SABAS ALONSO
Drywall Nailing 2/13/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 2/13/2026 Approved SABAS ALONSO
Shower Pan 2/13/2026 Approved SABAS ALONSO
Sewer 4/24/2026 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 4/24/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/6/2026 Corrections Issued SABAS ALONSO
Gas Test 5/6/2026 Approved SABAS ALONSO
HVAC-Final 5/13/2026 Approved SABAS ALONSO
PLUMBING-Final 5/13/2026 Approved SABAS ALONSO
Gas Test 5/19/2026 Approved LUIS CASTRO
Final 5/29/2026 Corrections Issued SABAS ALONSO
Green Building Final 5/29/2026 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 5/29/2026 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 5/29/2026 Approved SABAS ALONSO