3170 1/2 W LARGA AVE 90039
Certificate Information: 3170 1/2 W LARGA AVE 90039
- Application / Permit
- 25010-20000-04214
- Plan Check / Job No.
- B25VN26744
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 31'-10" X 43'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1) .
- Permit Issued
- Issued on 10/31/2025
- Issuing Office
- Current Status
- Issued on 10/31/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 9/17/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/19/2025 | APPLICANT |
| Plan Check Approved | 10/22/2025 | YAQUB MIRZA |
| Issued | 10/31/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 9/22/2025 | CINDY QI |
| ZI | Cleared | 9/26/2025 | DAVID URITA |
| Construction near power lines | Cleared | 10/9/2025 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2025 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 10/21/2025 | ROSE STEIN-WENDT |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/14/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 11/14/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 12/12/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Partial Approval | NICHOLAS LOPEZ |
| Insulation | 12/17/2025 | Partial Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 12/31/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Rough | 12/31/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 12/31/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2026 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 1/29/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Rough | 1/29/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Rough | 1/29/2026 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 1/29/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 1/29/2026 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 2/3/2026 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 2/3/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 2/11/2026 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 2/11/2026 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 2/13/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 2/13/2026 | Approved | NICHOLAS LOPEZ |
| Insulation | 2/24/2026 | Corrections Issued | GEM DE OCAMPO |
| Drywall Nailing | 3/6/2026 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 3/6/2026 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 3/6/2026 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 3/17/2026 | Partial Approval | NICHOLAS LOPEZ |
| Underground Mechanical | 3/20/2026 | Partial Approval | NICHOLAS LOPEZ |
| Sewer | 4/3/2026 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 4/27/2026 | Approved | NICHOLAS LOPEZ |