3170 1/2 W LARGA AVE 90039

Certificate Information: 3170 1/2 W LARGA AVE 90039

Application / Permit
25010-20000-04214
Plan Check / Job No.
B25VN26744
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'-10" X 43'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1) .
Permit Issued
Issued on 10/31/2025
Issuing Office
Current Status
Issued on 10/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/12/2025 APPLICANT
Assigned to Plan Check Engineer 9/17/2025 ARTIN ZARUKIAN
Corrections Issued 9/17/2025 ARTIN ZARUKIAN
Building Plans Picked Up 9/19/2025 APPLICANT
Plan Check Approved 10/22/2025 YAQUB MIRZA
Issued 10/31/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/22/2025 CINDY QI
Roof/Waste drainage to street Cleared 9/22/2025 CINDY QI
ZI Cleared 9/26/2025 DAVID URITA
Construction near power lines Cleared 10/9/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 10/21/2025 ROSE STEIN-WENDT
Sewer availability Cleared 10/21/2025 ROSE STEIN-WENDT

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/14/2025 Conditional Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 11/14/2025 Conditional Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 12/12/2025 Partial Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval NICHOLAS LOPEZ
Insulation 12/17/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 12/31/2025 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/31/2025 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Rough 12/31/2025 Not Ready for Inspection NICHOLAS LOPEZ
Verify Sprinkler Sign Off 12/31/2025 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/8/2026 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 1/29/2026 Corrections Issued NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 1/29/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 1/29/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 1/29/2026 Not Ready for Inspection NICHOLAS LOPEZ
Verify Sprinkler Sign Off 1/29/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 2/3/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 2/3/2026 Corrections Issued NICHOLAS LOPEZ
Interior/Exterior Lathing 2/11/2026 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 2/11/2026 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/13/2026 Approved NICHOLAS LOPEZ
Green Building Rough 2/13/2026 Approved NICHOLAS LOPEZ
Insulation 2/24/2026 Corrections Issued GEM DE OCAMPO
Drywall Nailing 3/6/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 3/6/2026 Approved NICHOLAS LOPEZ
Shower Pan 3/6/2026 Approved NICHOLAS LOPEZ
Underground Mechanical 3/17/2026 Partial Approval NICHOLAS LOPEZ
Underground Mechanical 3/20/2026 Partial Approval NICHOLAS LOPEZ
Sewer 4/3/2026 Approved NICHOLAS LOPEZ
Underground Mechanical 4/27/2026 Approved NICHOLAS LOPEZ