11742 W LA MAIDA ST 91607
Certificate Information: 11742 W LA MAIDA ST 91607
- Application / Permit
- 25010-20000-04183
- Plan Check / Job No.
- B25VN26598
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW ONE STORY DETACHED RECREATION ROOM WITH FULL BATHROOM WITH EXTERIOR ACCESS, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/14/2025
- Issuing Office
- Current Status
- CofO Issued on 8/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2025 | RARES BODEA |
| Assigned to Zoning Architect | 9/18/2025 | KAITA SAITO |
| Corrections Issued | 9/23/2025 | RARES BODEA |
| Quality Review Completed | 9/25/2025 | STEVEN KIM |
| Building Plans Picked Up | 9/25/2025 | APPLICANT |
| Plan Check Approved | 11/14/2025 | RARES BODEA |
| Issued | 11/14/2025 | APPLICANT |
| CofO in Progress | 7/20/2026 | JAVIER RAMOS JR |
| Permit Finaled | 8/4/2026 | RUBEN SALAS |
| CofO Issued | 8/4/2026 | RUBEN SALAS |
| Permit Finaled | 8/4/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2025 | STEVE MELGAR |
| Low Impact Development (LID) | Cleared | 9/25/2025 | MITESH PATEL |
| Specific Plan | Cleared | 9/26/2025 | CHRISTIAN PEARSON |
| Construction near power lines | Cleared | 10/15/2025 | GEVORK KARAPETYAN |
| Roof/Waste drainage to street | Cleared | 10/15/2025 | STEVE MELGAR |
| Zoning Plan Check | Cleared | 11/4/2025 | KAITA SAITO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/9/2025 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 12/10/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/10/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 12/11/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/16/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/3/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/4/2026 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2026 | Partial Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 2/4/2026 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 2/17/2026 | Not Ready for Inspection | MICHAEL CORTEZ |
| Shower Pan | 2/20/2026 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 2/20/2026 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/24/2026 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 2/24/2026 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 3/3/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/3/2026 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/19/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/19/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 5/6/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/17/2026 | Approved | JAVIER RAMOS JR |
| Final | 7/17/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| HVAC-Final | 7/17/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/17/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/17/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/17/2026 | Approved | JAVIER RAMOS JR |