7556 N GAVIOTA AVE 91406

Certificate Information: 7556 N GAVIOTA AVE 91406

Application / Permit
25010-20000-04128
Plan Check / Job No.
B25VN26159
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] NEW 2 STORY SFD PER SB9 WITH ATTACHED 1-CAR CARPORT
Permit Issued
Issued on 2/24/2026
Issuing Office
Current Status
Issued on 2/24/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2025 APPLICANT
Assigned to Plan Check Engineer 9/18/2025 JOSEPH RAFOLS
Assigned to Zoning Architect 9/18/2025 CAMERON JONES
Corrections Issued 9/22/2025 JOSEPH RAFOLS
Quality Review Completed 10/8/2025 SINA KHOSRAVI
Applicant returned to address corrections 2/3/2026 JOSEPH RAFOLS
Plan Check Approved 2/23/2026 JOSEPH RAFOLS
Issued 2/24/2026 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 9/30/2025 GEVORK KARAPETYAN
Address approval Cleared 10/20/2025 TONY CHIANG
Roof/Waste drainage to street Cleared 10/20/2025 TONY CHIANG
Eng Process Fee Ord 176,300 Cleared 10/21/2025 TONY CHIANG
Sewer availability Cleared 10/21/2025 TONY CHIANG
Hydrant and Access approval Cleared 10/30/2025 PATRICK PEREZ
Senate Bill 9 Cleared 1/16/2026 JASON CHAN
Zoning Plan Check Cleared 2/10/2026 CAMERON JONES

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 5140 YOLANDA AVE      TARZANA, CA 91356
Engineer Basma,, Ali J; Lic. No.: NA53080       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/27/2026 Corrections Issued MICHAEL CORTEZ
Footing/Foundation/Slab 4/29/2026 Conditional Approval KIRK SANDERS
Special/Order Compliance 4/29/2026 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 6/1/2026 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/1/2026 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 6/1/2026 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/4/2026 Corrections Issued MICHAEL CORTEZ
Floor/Roof Diaphrgm/Shear Wall 6/5/2026 Corrections Issued MICHAEL CORTEZ
BUILDING-Rough-Frame 7/22/2026 No Result Entered MICHAEL CORTEZ
ELECTRICAL-Rough 7/22/2026 No Result Entered MICHAEL CORTEZ
Floor/Roof Diaphrgm/Shear Wall 7/22/2026 No Result Entered MICHAEL CORTEZ
Gas Test 7/22/2026 No Result Entered MICHAEL CORTEZ
Green Building Rough 7/22/2026 No Result Entered MICHAEL CORTEZ
HVAC-Rough 7/22/2026 No Result Entered MICHAEL CORTEZ
PLUMBING-Rough 7/22/2026 No Result Entered MICHAEL CORTEZ
Verify Sprinkler Sign Off 7/22/2026 No Result Entered MICHAEL CORTEZ
Wood Frame 7/22/2026 No Result Entered MICHAEL CORTEZ