1165 E 47TH ST 90011

Certificate Information: 1165 E 47TH ST 90011

Application / Permit
25010-20000-04052
Plan Check / Job No.
B25VN25742
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1) SEE COMMENTS
Permit Issued
Issued on 2/20/2026
Issuing Office
Current Status
Issued on 2/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/2/2025 APPLICANT
Assigned to Plan Check Engineer 10/6/2025 CARLOS MONTES
Corrections Issued 10/7/2025 CARLOS MONTES
Applicant returned to address corrections 12/24/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 2/4/2026 NEHEMIAS RAMOS
Applicant returned to address corrections 2/11/2026 NEHEMIAS RAMOS
Plan Check Approved 2/19/2026 NEHEMIAS RAMOS
Issued 2/20/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/4/2025 ERIK BEASLEY
Roof/Waste drainage to street Cleared 12/4/2025 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/20/2026 XOCHITL ARQUIETA
Sewer availability Cleared 1/20/2026 XOCHITL ARQUIETA

Contact Information

Contractor Johnson Built; Lic. No.: 1120255-B       ,
Engineer Doan,, Patrick; Lic. No.: NA6215       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/24/2026 Partial Approval SABAS ALONSO
Sewer 2/24/2026 Approved SABAS ALONSO
Underground Mechanical 2/24/2026 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 3/4/2026 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/19/2026 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/26/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/31/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/31/2026 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/1/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/13/2026 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/13/2026 Partial Approval ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 4/13/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/16/2026 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 4/16/2026 Approved ALEJANDRO DE ARTOLA
Insulation 4/16/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/16/2026 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 4/20/2026 Approved ALEX COLIN