1926 S THAYER AVE 90025
Certificate Information: 1926 S THAYER AVE 90025
- Application / Permit
- 25010-20000-04049
- Plan Check / Job No.
- B25VN25726
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- (N) DETACHED PATIO COVER (16' X 9')
- Permit Issued
- Issued on 12/11/2025
- Issuing Office
- Current Status
- Issued on 12/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | NILOOFAR MEHRAIN |
| Assigned to Zoning Architect | 9/4/2025 | CAMERON JONES |
| Corrections Issued | 9/19/2025 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/22/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 9/25/2025 | APPLICANT |
| Applicant returned to address corrections | 12/2/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/11/2025 | NILOOFAR MEHRAIN |
| Issued | 12/11/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/23/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2025 | JESUS CISNEROS |
| Roof/Waste drainage to street | Cleared | 11/12/2025 | STEVE MELGAR |
| Specific Plan | Cleared | 11/18/2025 | RICHARD WOO |
| Zoning Plan Check | Cleared | 11/19/2025 | CAMERON JONES |
| GPI Written Notices | Cleared | 12/2/2025 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 12/2/2025 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 1/14/2026 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Barrier | 1/14/2026 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Subgrade | 1/14/2026 | Not Ready for Inspection | DANIEL VERA |
| Underground Mechanical | 1/14/2026 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 1/16/2026 | Partial Approval | DANIEL VERA |
| METHANE-Barrier | 1/16/2026 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Subgrade | 1/16/2026 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 1/26/2026 | Corrections Issued | RYAN SALAZAR |
| METHANE-Barrier | 2/6/2026 | Approved | CHRISTOPHER WILSON |
| METHANE-Subgrade | 2/6/2026 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2026 | Partial Approval | RYAN SALAZAR |
| Pre-Inspection | 2/23/2026 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/9/2026 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/19/2026 | Approved | RYAN SALAZAR |
| METHANE-Rough | 3/19/2026 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 3/19/2026 | Approved | RYAN SALAZAR |