5835 1/4-1/2 N CARTWRIGHT AVE 91601

Certificate Information: 5835 1/4-1/2 N CARTWRIGHT AVE 91601

Application / Permit
25010-20000-04048
Plan Check / Job No.
B25VN25723
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW 2-UNIT 2-STORY ACCESSORY DWELLING UNITS TO COMPLY WITH GCS 66323(a)(4) PER ENGINEERING
Permit Issued
Issued on 11/24/2025
Issuing Office
Current Status
Issued on 11/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/4/2025 APPLICANT
Assigned to Plan Check Engineer 9/11/2025 ALFRED RAMIREZ
Assigned to Zoning Architect 9/11/2025 RONALD GREENE
Corrections Issued 9/18/2025 ALFRED RAMIREZ
Quality Review Completed 9/24/2025 STEVEN KIM
Applicant returned to address corrections 11/4/2025 ALFRED RAMIREZ
Plan Check Approved 11/13/2025 ALFRED RAMIREZ
Plan Check Approved 11/18/2025 ALFRED RAMIREZ
Issued 11/24/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/19/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/19/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 9/19/2025 DAVID LOPEZ
Sewer availability Cleared 9/19/2025 DAVID LOPEZ
Zoning Plan Check Cleared 9/29/2025 Ronald Greene

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/12/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/12/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Sewer 2/12/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/12/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/13/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/13/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/26/2026 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 2/26/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/20/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Wood Frame 3/20/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Deputy Wood Construction 3/23/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/31/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/1/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/1/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/7/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/7/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/7/2026 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 4/7/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/10/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/10/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/17/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/17/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/17/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/17/2026 Approved ROBERTO PALACIOS-LOPEZ
Insulation 4/28/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/28/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 5/4/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/4/2026 Approved GAREN HAYRAPETYAN