465-465 1/2 E 30TH ST 90011
Certificate Information: 465-465 1/2 E 30TH ST 90011
- Application / Permit
- 25010-20000-04028
- Plan Check / Job No.
- B25VN25605
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New detached 2 story- 2 unit ADU per GCS 66323(a)(4) . To be fully sprinklered NFPA 13D
- Permit Issued
- Issued on 12/16/2025
- Issuing Office
- Current Status
- Issued on 12/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2025 | MARCELA FRANQUEZ |
| Assigned to Zoning Architect | 9/18/2025 | MELISSA QUINONES |
| Corrections Issued | 9/20/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 10/1/2025 | TU HUA |
| Applicant returned to address corrections | 10/31/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 12/2/2025 | MARCELA FRANQUEZ |
| Issued | 12/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 9/23/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/23/2025 | MICHAEL BROWN |
| Zoning Plan Check | Cleared | 10/21/2025 | Sunmin Lee |
Contact Information
| Contractor | Arash Mofakham; Lic. No.: 1035634-B | , |
| Contractor | Mofakham Arash; Lic. No.: 1035634-B | , |
| Engineer | Aalam,, Yahya; Lic. No.: C94318 | 3111 4TH ST APT 401 SANTA MONICA, CA 90405 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2026 |
Inspection Request History
| Pre-Inspection | 2/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 2/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/6/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/11/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/11/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/16/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 4/1/2026 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 4/6/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/1/2026 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 5/1/2026 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 5/1/2026 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/6/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/18/2026 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 5/18/2026 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 5/18/2026 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/5/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/5/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/5/2026 | Approved | ALEJANDRO DE ARTOLA |