7350 N COZYCROFT AVE 91306

Certificate Information: 7350 N COZYCROFT AVE 91306

Application / Permit
25010-20000-04015
Plan Check / Job No.
B25VN25546
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
Permit Issued
Issued on 1/26/2026
Issuing Office
Current Status
Issued on 1/26/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/3/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 KHEDER ALRAZAA
Assigned to Zoning Architect 9/4/2025 AMIR NAKHLA
Corrections Issued 9/6/2025 KHEDER ALRAZAA
Quality Review Completed 9/9/2025 GARO TELMI
Applicant returned to address corrections 11/6/2025 KHEDER ALRAZAA
Applicant returned to address corrections 12/3/2025 KHEDER ALRAZAA
Applicant returned to address corrections 12/22/2025 KHEDER ALRAZAA
Plan Check Approved 1/14/2026 KHEDER ALRAZAA
Issued 1/26/2026 APPLICANT

Permit Application Clearance Information

Zoning Plan Check Cleared 11/4/2025 AMIR NAKHLA
Address approval Cleared 11/6/2025 WALLIE JONG
Construction within easement Cleared 11/6/2025 GEVORK KARAPETYAN
Roof/Waste drainage to street Cleared 11/6/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/2/2025 WALLIE JONG
Sewer availability Cleared 12/2/2025 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/4/2026 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 2/9/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 2/9/2026 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 2/12/2026 Approved ALEXANDER HANDY
Footing/Foundation/Slab 2/12/2026 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Partial Approval ALEXANDER HANDY
Verify Sprinkler Sign Off 2/23/2026 Not Ready for Inspection ALEXANDER HANDY
Sewer 2/24/2026 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Partial Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2026 Not Ready for Inspection DAVID FASTIGGI
Deputy Wood Construction 3/4/2026 Conditional Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 3/6/2026 Corrections Issued ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 3/6/2026 Approved ALEXANDER HANDY
HVAC-Rough 3/13/2026 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 3/20/2026 Corrections Issued ALEXANDER HANDY
HVAC-Rough 3/20/2026 Partial Approval ALEXANDER HANDY
Verify Sprinkler Sign Off 3/20/2026 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 3/25/2026 Corrections Issued DAVID FASTIGGI
Interior/Exterior Lathing 3/25/2026 Not Ready for Inspection DAVID FASTIGGI
Verify Sprinkler Sign Off 3/25/2026 Not Ready for Inspection DAVID FASTIGGI
Interior/Exterior Lathing 3/26/2026 Approved DAVID FASTIGGI
BUILDING-Rough-Frame 4/13/2026 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 4/22/2026 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 4/29/2026 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 5/11/2026 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 5/20/2026 Approved ALEXANDER HANDY
Green Building Rough 5/20/2026 Approved ALEXANDER HANDY
Insulation 5/20/2026 Approved ALEXANDER HANDY
Drywall Nailing 5/27/2026 Approved ALEXANDER HANDY
Interior/Exterior Lathing 5/27/2026 Approved ALEXANDER HANDY
Shower Pan 5/27/2026 Approved ALEXANDER HANDY