11011 N DARBY AVE 91326

Certificate Information: 11011 N DARBY AVE 91326

Application / Permit
25010-20000-03982
Plan Check / Job No.
B25VN25309
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(A)(2)
Permit Issued
Issued on 9/9/2025
Issuing Office
Current Status
CofO in Progress on 7/12/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/29/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 JEROME MAGAT PALMA
Corrections Issued 9/5/2025 JEROME MAGAT PALMA
Building Plans Picked Up 9/8/2025 APPLICANT
Plan Check Approved 9/9/2025 ALEC MOUSAKHANIAN
Issued 9/9/2025 APPLICANT
CofO in Progress 6/25/2026 JACK KARGODORIAN
No Progress 7/12/2026 CHRISTOPHER WILSON
CofO in Progress 7/12/2026 CHRISTOPHER WILSON

Permit Application Clearance Information

Address approval Cleared 9/8/2025 JESUS CISNEROS
Construction near power lines Cleared 9/8/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 9/8/2025 JESUS CISNEROS
Roof/Waste drainage to street Cleared 9/8/2025 WALLIE JONG
Sewer availability Cleared 9/8/2025 JESUS CISNEROS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 12/2/2025 Partial Approval DAVID SCANTLIN
Sewer 12/2/2025 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 12/12/2025 Approved DAVID SCANTLIN
Footing/Foundation/Slab 12/12/2025 Approved DAVID SCANTLIN
Underground Mechanical 12/12/2025 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 12/22/2025 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval DAVID SCANTLIN
Green Building Rough 12/22/2025 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 12/22/2025 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 12/22/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 1/29/2026 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Approved DAVID SCANTLIN
Green Building Rough 1/29/2026 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 1/29/2026 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 1/29/2026 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 1/29/2026 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 3/2/2026 Approved DAVID SCANTLIN
Green Building Rough 3/2/2026 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/2/2026 Partial Approval DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 3/2/2026 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 3/2/2026 Approved DAVID SCANTLIN
Insulation 3/12/2026 Approved DAVID SCANTLIN
Shower Pan 3/12/2026 Approved DAVID SCANTLIN
Drywall Nailing 3/25/2026 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/25/2026 Approved DAVID SCANTLIN
Final 6/11/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 6/11/2026 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/11/2026 SGSOV Not Ready JACK KARGODORIAN
Service/Power Release 6/11/2026 Approved JACK KARGODORIAN
Smoke Detectors 6/11/2026 Approved JACK KARGODORIAN
Final 6/24/2026 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/24/2026 SGSOV Approved JACK KARGODORIAN
Special/Order Compliance 7/13/2026 Corrections Issued JACK KARGODORIAN