10896-10898 W VALERIO ST 91352
Certificate Information: 10896-10898 W VALERIO ST 91352
- Application / Permit
- 25010-20000-03961
- Plan Check / Job No.
- B25VN25220
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR SHAPED 2 STORY 37'-3" x 48'-3" DWELLING UNIT PER SB9 W/ ATT. ACCESSORY DWELLING UNIT; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 11/13/2025
- Issuing Office
- Current Status
- CofO Issued on 7/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | SEAN SHAHMIRI |
| Assigned to Zoning Architect | 9/4/2025 | ELAHE MERRIKHI |
| Corrections Issued | 9/10/2025 | SEAN SHAHMIRI |
| Quality Review Completed | 9/12/2025 | STEVEN KIM |
| Building Plans Picked Up | 9/15/2025 | APPLICANT |
| Applicant returned to address corrections | 11/13/2025 | SEAN SHAHMIRI |
| Plan Check Approved | 11/13/2025 | SEAN SHAHMIRI |
| Issued | 11/13/2025 | APPLICANT |
| CofO in Progress | 7/6/2026 | RAUL OLAGI |
| Permit Finaled | 7/17/2026 | DANIEL ORRANTE |
| CofO Issued | 7/17/2026 | DANIEL ORRANTE |
| Permit Finaled | 7/17/2026 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2025 | KIMBERLY HERNANDEZ |
| Senate Bill 9 | Cleared | 9/25/2025 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2025 | ABEL CASILLAS |
| Hydrant and Access approval | Cleared | 10/15/2025 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 10/15/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 10/15/2025 | ABEL CASILLAS |
| Zoning Plan Check | Cleared | 11/10/2025 | ELAHE MERRIKHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/24/2025 | Partial Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/24/2025 | Corrections Issued | MICHAEL CORTEZ |
| Underground Mechanical | 11/26/2025 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 12/10/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 12/15/2025 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 12/15/2025 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 12/16/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2026 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 2/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 2/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 2/18/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 2/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 2/23/2026 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 2/23/2026 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 2/26/2026 | Approved | JAVIER RAMOS JR |
| Insulation | 2/26/2026 | Approved | JAVIER RAMOS JR |
| Sewer | 4/6/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 4/6/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 6/10/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 6/10/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/2/2026 | OK to Issue CofO | RAUL OLAGI |
| Footing/Foundation/Slab | 7/2/2026 | Approved | RAUL OLAGI |
| Green Building Final | 7/2/2026 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 7/2/2026 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 7/2/2026 | Approved | RAUL OLAGI |
| Smoke Detectors | 7/2/2026 | Approved | RAUL OLAGI |