10896-10898 W VALERIO ST 91352

Certificate Information: 10896-10898 W VALERIO ST 91352

Application / Permit
25010-20000-03961
Plan Check / Job No.
B25VN25220
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR SHAPED 2 STORY 37'-3" x 48'-3" DWELLING UNIT PER SB9 W/ ATT. ACCESSORY DWELLING UNIT; NFPA-13D THRU-OUT
Permit Issued
Issued on 11/13/2025
Issuing Office
Current Status
CofO Issued on 7/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 SEAN SHAHMIRI
Assigned to Zoning Architect 9/4/2025 ELAHE MERRIKHI
Corrections Issued 9/10/2025 SEAN SHAHMIRI
Quality Review Completed 9/12/2025 STEVEN KIM
Building Plans Picked Up 9/15/2025 APPLICANT
Applicant returned to address corrections 11/13/2025 SEAN SHAHMIRI
Plan Check Approved 11/13/2025 SEAN SHAHMIRI
Issued 11/13/2025 APPLICANT
CofO in Progress 7/6/2026 RAUL OLAGI
Permit Finaled 7/17/2026 DANIEL ORRANTE
CofO Issued 7/17/2026 DANIEL ORRANTE
Permit Finaled 7/17/2026 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/25/2025 KIMBERLY HERNANDEZ
Senate Bill 9 Cleared 9/25/2025 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 10/15/2025 ABEL CASILLAS
Hydrant and Access approval Cleared 10/15/2025 LAVEON RIDER
Roof/Waste drainage to street Cleared 10/15/2025 ABEL CASILLAS
Sewer availability Cleared 10/15/2025 ABEL CASILLAS
Zoning Plan Check Cleared 11/10/2025 ELAHE MERRIKHI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/24/2025 Partial Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/24/2025 Corrections Issued MICHAEL CORTEZ
Underground Mechanical 11/26/2025 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 12/10/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 12/15/2025 Partial Approval JOSE AVILA
Footing/Foundation/Slab 12/15/2025 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 12/16/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/12/2026 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/9/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/12/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/17/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/17/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/18/2026 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/18/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/18/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/18/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 2/18/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/18/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 2/18/2026 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/23/2026 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 2/23/2026 Approved MICHAEL CORTEZ
Drywall Nailing 2/26/2026 Approved JAVIER RAMOS JR
Insulation 2/26/2026 Approved JAVIER RAMOS JR
Sewer 4/6/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 4/6/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 6/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 6/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/2/2026 OK to Issue CofO RAUL OLAGI
Footing/Foundation/Slab 7/2/2026 Approved RAUL OLAGI
Green Building Final 7/2/2026 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 7/2/2026 SGSOV Approved RAUL OLAGI
Service/Power Release 7/2/2026 Approved RAUL OLAGI
Smoke Detectors 7/2/2026 Approved RAUL OLAGI